  • Question 131:

    Which tool or technique is used in Close Procurements?

    A. Contract plan

    B. Procurement plan

    C. Closure process

    D. Procurement audits

  • Question 132:

    In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

    A. Start-to-start (SS)

    B. Start-to-finish (SF)

    C. Finish-to-finish (FF)

    D. Finish-to-start (FS)

  • Question 133:

    A required input for Create WBS is a project:

    A. quality plan.

    B. schedule network.

    C. management document update.

    D. scope statement.

  • Question 134:

    Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

    A. -8000

    B. -2000

    C. 2000

    D. 8000

  • Question 135:

    Which type of risk diagram is useful for showing time ordering of events?

    A. Ishikawa

    B. Milestone

    C. Influence

    D. Decision tree

  • Question 136:

    What is a tool to improve team performance?

    A. Staffing plan

    B. External feedback

    C. Performance reports

    D. Co-location

  • Question 137:

    Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

    A. Cause and effect diagram

    B. Control charts

    C. Pareto chart

    D. Histogram

  • Question 138:

    What is the primary benefit of meeting quality requirements?

    A. Quality metrics

    B. Less rework

    C. Quality control measurements

    D. Benchmarking

  • Question 139:

    The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

    A. 1.33

    B. 2

    C. 0.75

    D. 0.5

  • Question 140:

    A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

    A. Three weeks

    B. Four weeks

    C. Five weeks

    D. Six weeks

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.