Question 35 of 49
0% complete
Q35 Single choice

A customer has a new EMC Avamar server with four 3.9 TB data nodes. This server is backing up two Avamar clients. The first client has 8 GB of RAM and two file systems. The first file system has 3 million files consuming .75 TB. The second file system contains 5 million files consuming 1 TB of space. The second client has 10 GB of RAM and one file system containing 4 million files is consuming 1.2 TB of space. Both clients will belong to the same backup group.

How long will the steady state backup group be expected to run?