Q14
Single choice
Refer to the exhibit.

You are expanding the compute layer of a VDC, and need to add more access layer switches to provide connectivity to the hypervisors. However, there are no available ports on the two aggregation layer switches to accommodate the uplink connections from the new access layer switches, and all uplinks are active and operating at 95% of capacity.
Your design must satisfy all of the following requirements:
- Expand the access layer
- Maintain the same configuration as the existing environment
- Maintain the performance of the existing environment.
The CIO has authorized you to purchase additional
aggregation layer switches if needed.
What should you recommend?