Q45
Single choice
The question below is based on the following information:
Beginning inventory = 43
Week 1 | Week 2 | Week 3
Forecast: 20 | 20 | 20
Customer orders: 22 | 17 | 10
Projected on-hand: ?
Master production schedule (MPS): - | - | 80
Available-to-promise (ATP): ?
What is the largest customer order that could be accepted for delivery at the end of week 3 without making changes to the master production schedule (MPS)?