Q94 Single choice Mark for later In a project, total float measures the: A Ability to shuffle schedule activities to lessen the duration of the project. B Amount of time an activity can be extended or delayed without altering the project finish date. C Cost expended to restore order to the project schedule after crashing the schedule. D Estimate of the total resources needed for the project after performing a forward pass. Correct answer