Question 17 of 70
0% complete
Q17 Single choice

Your company is migrating its workloads to Google Cloud due to an expiring data center contract. The on-premises environment and Google Cloud are not connected. You have decided to follow a lift-and-shift approach, and you plan to modernize the workloads in a future project. Several old applications connect to each other through hard-coded internal IP addresses. You want to migrate these workloads quickly without modifying the application code. You also want to maintain all functionality.

What should you do?