Q11
Single choice
An architect is updating a design document in preparation for an expansion of their organization's existing VCF environment. Following the completion of a capacity assessment, a new cluster will be deployed to support the hosting of future application deployments. Due to restrictions on the availability of budget for the project, the hardware for the additional cluster has already been procured and there is no additional budget available for future procurements.
What should the architect include within the design documentation based on this approach?