1Z0-902 Web TestEngine demo

Exit VCEDump 1Z0-902 Oracle Exadata Database Machine X9M Implementation Essentials
Question 6 of 9
0% complete
Q6 Single choice

Examine these commands:

1. Execute "crscti stop cluster -all" as the grid user from one database server.

2. Execute "crscti stop cluster -all" as root from one database server.

3. Power off all network switches.

4. Execute "crscti stop cluster" as root from one database server.

5. Execute "crscti stop cluster" as the grid user from one database server.

6. Power off the rack using the power switches on the PDUs.

7. Execute "shutdown -h now" on all database servers.

8. Execute "shutdown -h now" on all Exadata storage servers.

Which is the correct order or the required commands to completely power off an Exadata Database Machine in an orderly fashion?

Sign in to mark questions

Sign in to save marked questions and return to this demo.