Q20 Single choice

A utility company sees several 'New Connect' activities being added to the routing bucket throughout the day.

They want 'Meter Read' activities to potentially be removed from the technician's route so that the 'New Connect' activities can be assigned if the technician qualifies for the activity.

They enabled reoptimization in their routing plan and created a reoptimization filter targeting the 'Meter Read' activities.

What additional settings are required in the routing plan to meet the desired behavior?