A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand for this product and wants it to launch as soon as possible. What should the project manager do to realize this opportunity?
-
A
Communicate with the industry's regulatory authority to grant the company an exception.
-
B
Escalate the issue to the company's CEO who has experience with the regulations.
-
C
Comply with the regulatory requirements and work to compress the project schedule.
-
D
Hire a third party who is an expert on the industry's regulations to work out the details.
Reveal answer details
Close answer details
One of the team members is always late to the daily standup meeting. What should the project manager do?
-
A
Schedule the meeting at the end of the day to accommodate everyone.
-
B
Ignore the situation since the team member is accomplishing their deliverables.
-
C
Reinforce the ground rules for standup meetings with the entire team.
-
D
Speak with the team member directly to reinforce the ground rules.
Reveal answer details
Close answer details
There are several dependent work streams in a project. Some project stakeholders feel that coordination among project team members and progress visibility are lacking. What should the project manager do?
-
A
Escalate the concerns to the project steering committee.
-
B
Review and update the communications management plan.
-
C
Organize a team meeting to review the project status.
-
D
Discuss the concerns with the project sponsor.
Reveal answer details
Close answer details
The project manager just started leading a project team from which the previous project manager resigned. After a quick evaluation of the project, it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule. What should the project manager do?
-
A
Conduct a meeting with the project team to discuss and address the sources of disagreement
-
B
Inform the stakeholders that the project will be delayed due to previous team management
-
C
Crash the project timeline to ensure the project is back on schedule
-
D
Issue a change request to extend the project schedule based on identified delays
Reveal answer details
Close answer details
During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?
-
A
Identify the problem's root causes and define the ground rules with all project team members to minimize interferences
-
B
Hire a coach to help all project teams to improve their abilities to solve problems on their own.
-
C
Reunite with the project team members affected and tell them not to reduce the team's capacity
-
D
Recommend to the project team members that they should improve their planning and make their stones smaller
Reveal answer details
Close answer details
An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures. What should the project manager do to help avoid this situation in the future?
-
A
Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace
-
B
Review the velocity of the team over the last several sprnts and adjust the plan accordingly
-
C
Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan
-
D
Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap
Reveal answer details
Close answer details
A project manager is using a subcontractor for mobile application development. When the project team tests the application, they realize it does not comply with the new company user-interface standards. Even though these new standards were not included in the statement of work (SOW), the subcontractor agrees to the additional scope as long as payment for this additional work is paid immediately. What should the project manager do?
-
A
Negotiate new pricing based on the revised estimations from the subcontractor that reflect the new work.
-
B
Initiate a change request and review the contract to evaluate the payment options before responding.
-
C
Deny the subcontractor's payment request, because the product does not comply with the project needs and close the project.
-
D
Initiate a change to incorporate an immediate payment milestone in the contract as per the subcontractor's request.
Reveal answer details
Close answer details
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain. What should the project manager do now?
-
A
Reduce the priority of project risks as all remaining risks are low-level
-
B
Notify stakeholders that all high-level risks have been resolved
-
C
Reevaluate identified risks and update the risk register
-
D
Reclassify low-level risks as high-level risks
Reveal answer details
Close answer details
A food company is developing a new product using a predictive approach, and the product is currently in the testing phase. Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach. At the end of one of the iterations, a new regulation related to the product is enacted. What should the project manager do next?
-
A
Make a change request regarding the project's scope to ensure compliance.
-
B
Include an assessment to verfy compliance in the next iteration
-
C
Conduct an iteration review to address the new regulation
-
D
Start the tests over, adapting the trials to the new regulation
Reveal answer details
Close answer details
Question 10
Single choice
A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event. What should the project manager do first?
-
A
Follow the risk response plan
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 11
Single choice
During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?
-
A
Check the approved list of requirements to see if there are any missing items.
-
B
Work with the stakeholder to improve the requirements' acceptance criteria
-
C
Review the requirements traceability matrix with the concerned stakeholder
-
D
Discuss with the stakeholder which additional requirements should be added
Reveal answer details
Close answer details
Question 12
Single choice
Upon analyzing the report requirements to create a functional design, the project team finds that the information source is not correct and needs to be adjusted. What should the project manager do?
-
A
Initiate a change request procedure.
-
B
Build a prototype to verify the information.
-
C
Consult with subject matter experts (SMEs).
-
D
Review the statement of work (SOW).
Reveal answer details
Close answer details
Question 13
Single choice
A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product. What should the project manager do?
-
A
Use the remaining time and resources to add additional scope to the project without spending the project budget.
-
B
Ensure product quality by spending the remaining resources and time on additional quality checks for the product.
-
C
Acknowledge the project closure criteria has been met and release the remaining budget and resources.
-
D
Obtain approval from the sponsor to add additional functionality to the project deliverables with the leftover budget.
Reveal answer details
Close answer details
Question 14
Single choice
A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 15
Single choice
A customer interacts directly with a Scrum team and continually requests changes in priorities. This causes confusion among the team members and they complain to the project manager. What should the project manager do?
-
A
Advise the customer to discuss changes with the product owner.
-
B
Document this issue in the sprint backlog for discussion at a team meeting.
-
C
Ask the customer to submit a change request to the project sponsor.
-
D
Encourage the team to clarify the requests with the customer.
Reveal answer details
Close answer details
Question 16
Single choice
A project manager is leading the first agile project for the organization. During the kick-off meeting, the project manager notices that the team does not have the same understanding about agile approaches. The project manager is concerned about the impact of that confusion. What should the project manager do to address this situation?
-
A
Evaluate the possibility of managing this project using a predictive approach.
-
B
Submit a change request for a new team that has agile experience.
-
C
Mentor the team to explain agile principles and create a shared understanding.
-
D
Hire a functional manager who is familiar with agile methodologies.
Reveal answer details
Close answer details
Question 17
Single choice
During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected. What should the project manager have the project team do first to address the issue?
-
A
Update the issue log and document the change
-
B
Review the product specification requirements.
-
C
Perform a root cause analysis
-
D
Submit a change request for corrective action.
Reveal answer details
Close answer details
Question 18
Single choice
By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the project lead use to handle the situation?
-
A
Informal written communication, such as a friendly reminder.
-
B
Formal written communication, such as an email with a copy sent to the manager.
-
C
Informal verbal communication, such as a conversation.
-
D
Formal verbal communication, such as a conversation at the end of the sprint retrospective.
Reveal answer details
Close answer details
Question 19
Single choice
A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements. How should the project manager resolve this issue?
-
A
Assist the team in estimating project tasks such as milestones and story points.
-
B
Gather the project team and product owner to find a solution design.
-
C
Review issues and identify opportunities for improvement that add value to the product.
-
D
Ask the team to rework the definition of done (DoD) before items can be pulled into the backlog.
Reveal answer details
Close answer details
Question 20
Multiple choice
A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met. Which three actions should the project manager do? (Choose three.)
-
A
Identify in the iteration planning the acceptance criteria that meet quality standards.
-
B
Identify the acceptance criteria during the retrospective that meet the quality standards.
-
C
Analyze the lessons learned to determine appropriate testing metrics in quality standards.
-
D
Incorporate performance metrics on the verified deliverables according to quality standards.
-
E
Perform a risk analysis to determine the impact of not complying with quality standards.
Reveal answer details
Close answer details
Question 21
Single choice
It is late at night on a weekend when a team member calls the project manager on the telephone. The team member is crying about the pressures of an upcoming deadline. What should the project manager do?
-
A
Ask the team member to send their concerns in writing.
-
B
Empathize with the team member and discuss next steps.
-
C
Review the organization's human resources (HR) policy.
-
D
Schedule a meeting with the team member for the next work day.
Reveal answer details
Close answer details
Question 22
Single choice
local company is developing a new product and. for the first time, using a remote team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings. How should the project manager address this situation?
-
A
Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.
-
B
Document the risk in the risk management plan and use contingency reserves to hire a local vendor.
-
C
Review lessons learned from previous projects and organizational process assets (OPAs).
-
D
Determine the communication needs, environment, and tools to get the message across.
Reveal answer details
Close answer details
Question 23
Single choice
A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?
-
A
Work with the product owner to evaluate and prioritize the requirements
-
B
Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list
-
C
Determine the expected benefits of each requirement to maximize the overall business value
-
D
Prioritize the requirements based on the hierarchical level of the requesting stakeholders
Reveal answer details
Close answer details
Question 24
Single choice
In the past, the project manager and the project team performed well using predictive methodology. However, the organization recently decided to adopt agile approaches, and the project sponsor wants to use an agile approach in an upcoming project. Before initiating the project, what should the project manager do?
-
A
Prepare a risk report that captures the probability and impact of risks, and then share it with the project sponsor.
-
B
Share the organization's decision with the team and make plans to adopt an agile approach in the upcoming project.
-
C
Make a request to human resources for new team members who have agile experience.
-
D
Ask the project sponsor to change the approach back to predictive as that is the team's strength.
Reveal answer details
Close answer details
Question 25
Multiple choice
A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides with the company's financial budget planning period. Which two actions should the project manager take next to address this concern? (Choose two.)
-
A
Advise the sponsor that it is not feasible to determine if the end date will be met as the project is in the initiation phase.
-
B
Facilitate a risk workshop with all stakeholders in attendance to identify and assess all risks to the project.
-
C
Log the concern as a risk in the project risk register and assess the impact and severity of the risk.
-
D
Change the project implementation date so that the concern is alleviated and no longer applicable.
-
E
Communicate to the project sponsor that the implementation date is low risk and will not impact the project.
Reveal answer details
Close answer details
Question 26
Single choice
A project manager has noticed that the performance of a new team member has increased dramatically over the past few months. The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member. The project manager wants to formally record the team member's success in the project documentation. What should the project manager do?
-
A
Attach a note to the project management plan about the team member
-
B
Hold a project team meeting about the team member's contribution and take minutes
-
C
Record the team member's contribution in the responsibility assignment matrix (RAM)
-
D
Send a communication to management recognizing the team member's contributions
Reveal answer details
Close answer details
Question 27
Single choice
A project manager is leading a software development project using agile practices and has outsourced work to three well-qualified subcontractors. Over time, problems arise related to supply chain management, and the project manager considers replacing the subcontractors with new suppliers. What should the project manager have done to avoid this problem?
-
A
Hired more Scrum Masters so that each Scrum Master manages one supplier.
-
B
Escalated the issue to the product owner to seek possible solutions.
-
C
Engaged the suppliers by category and validated the strategy with stakeholders.
-
D
Created user stories for the suppliers and saved their qualification records in the backlog.
Reveal answer details
Close answer details
Question 28
Single choice
A project manager presents the project schedule to the customer, including the detailed phases for the entire project. The customer complains that the project timeline is longer than expected and does not want to wait until the end to see results. What should the project manager do first?
-
A
Adjust the project schedule to include additional resources for all project tasks.
-
B
Submit a change request to extend the project timeline.
-
C
Evaluate the impact of changing the project framework to an incremental approach.
-
D
Apply crashing techniques to all activities in the project schedule.
Reveal answer details
Close answer details
Question 29
Single choice
All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day. What should the project manager do to prevent these delays?
-
A
Review the Pareto diagram to identify the source of delays.
-
B
Meet with the team in 2 weeks to respond to all of the open tasks.
-
C
Consolidate the decision-making authority to remain with the project manager.
-
D
Delegate the decision-making authority of some tasks to the team.
Reveal answer details
Close answer details
Question 30
Single choice
During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?
-
A
Update the risk register and implement the approved risk response plan for quality deviations.
-
B
Identify the resources that were responsible for the deliverable and request a team development plan.
-
C
Update the issue log, identify the involved stakeholders, and assign resources to the corrective actions.
-
D
Submit a change request to update the project quality requirements for the involved project deliverable.
Reveal answer details
Close answer details
Question 31
Single choice
A project manager is leading a highly visible project with a critical time constraint. Frequent scope changes have been well-managed with change control, but there have been misunderstandings among project team members. What should the project manager do?
-
A
Communicate to the team the need to organize common ground rules.
-
B
Organize training sessions and bonding activities for all team members.
-
C
Communicate changes regularly to ensure all team members are aligned.
-
D
Introduce new products and team support tools during project preparation.
Reveal answer details
Close answer details
Question 32
Single choice
During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming. What should the project manager have done to avoid this situation?
-
A
Determined the appropriate type of incentive for key team members
-
B
Conducted frequent monitoring on key team members' performance during project execution
-
C
Distributed the monetary incentive according to the team members' individual performance
-
D
identified the underperforming team members and asked the human resources (HR) department to replace them
Reveal answer details
Close answer details
Question 33
Single choice
A project manager is asked to negotiate between two team members who frequently have misunderstandings in order to reach an agreement that will advance the project. What should the project manager to?
-
A
Establish common ground through collaboration and understanding the team members' needs
-
B
Organize a team-building event to improve the morale among team members
-
C
Encourage a positive ongoing relationship between both of the team members
-
D
Coach and mentor the team members to build consensus and to resolve the ongoing conflict
Reveal answer details
Close answer details
Question 34
Single choice
A company's project management office (PMO) has started to implement iterative tools. A project manager is starting a new project and has identified an opportunity to use the iterative tools. One of the senior managers is concerned about this modified framework as it is fairly new to the company. What should the project manager do first?
-
A
Organize individual sessions with the stakeholders to build awareness and trust in the new framework
-
B
Look for external training on the new framework to eliminate the risk of low engagement from stakeholders.
-
C
Send documentation to the senior manager about the advantages of the new framework
-
D
Escalate the senior manager's concern to the project sponsor and distribute the status to the team
Reveal answer details
Close answer details
Question 35
Single choice
A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later, the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget. What should the project manager have done to prevent this from happening?
-
A
Reviewed the acceptance criteria and obtained client approval.
-
B
Allocated a risk budget for any post-release improvements.
-
C
Conducted a pilot to understand the client's performance parameters.
-
D
Established meetings with the client throughout the project phases.
Reveal answer details
Close answer details
HOTSPOT A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck. Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck. 
Reveal answer details
Close answer details
Question 37
Single choice
The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager, which gives the impression that the project is out of control. The project manager has been providing the project's status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings. What should the project manager do first to address this situation?
-
A
Evaluate the communication needs to discover the gaps and adjust the original plan if needed.
-
B
Use the contingency reserves to implement fast tracking and improve the schedule key performance indicators (KPIs).
-
C
Review the resource breakdown structure (RBS) to request the main stakeholder's manager to replace the stakeholder.
-
D
Provide evidence to the project sponsor that the project is on track and the communications have been sent.
Reveal answer details
Close answer details
Question 38
Single choice
In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?
-
A
Facilitate a meeting with the stakeholders and product owner to clarify the new need,
-
B
Update the acceptance criteria documentation to clearly reflect what was approved.
-
C
Review the new requirement and update all the stakeholders accordingly.
-
D
Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.
Reveal answer details
Close answer details
Question 39
Single choice
A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted. What approach should the project manager take to remove this impediment?
-
A
Follow a predictive approach in order to obtain formal acceptance of each deliverable
-
B
Work with the product owner to define the minimum viable product(s)
-
C
Reinforce the negotiation and soft skills of the team through training
-
D
Develop and monitor a plan with due dates to reduce the time of completing the product
Reveal answer details
Close answer details
Question 40
Single choice
This graph describes the current performance of a project in relation to cost and schedule. What should the project manager do to bring the project back on track? 
-
A
Review project cost because the project is over budget and ahead of schedule
-
B
Review project schedule and cost because the project is over budget and behind schedule
-
C
Review project schedule because the project is under budget and behind schedule
-
D
Review project scope because the project is under budget and ahead of schedule
Reveal answer details
Close answer details
Question 41
Single choice
A project manager recently took over an ongoing project. Within a few weeks, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause of this?
-
A
Undefined change control process
-
B
Unidentified project risks
-
C
Improper work breakdown structure (WBS)
-
D
Reveal answer details
Close answer details
Question 42
Single choice
A project manager has been assigned to a new agile project with rapidly changing knowledge areas. How should the project manager manage knowledge transfer on this project?
-
A
Require stakeholders to fully document all domain knowledge before starting.
-
B
Mentor the team and stakeholders to ensure that domain knowledge is exchanged during sprints.
-
C
Ask the team to set up initial sprints for knowledge transfer before focusing on deliverables.
-
D
Work with quality assurance (QA) to ensure that domain knowledge is transferred properly among stakeholders.
Reveal answer details
Close answer details
Question 43
Single choice
One team member is not as active as the rest of the team during a brainstorming session. The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired. The team member appreciates the project manager's concern. The project manager then decides to change the time and room for the meeting to ensure everyone can participate. What interpersonal skill did the project manager use?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 44
Single choice
After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project. How should the project manager handle this situation?
-
A
Comply with the project sponsor's request to not archive the project artifacts.
-
B
Consult with the project management office (PMO) for guidance on project artifacts.
-
C
Archive the project artifacts on the project manager's local computer for future reference.
-
D
Document the project sponsor's instructions as the archived project artifacts.
Reveal answer details
Close answer details
Question 45
Single choice
A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community. How should the project manager handle this issue?
-
A
Disregard these stakeholders since the relevant documents have been secured to execute this project.
-
B
Update the stakeholder register and risk management plan.
-
C
Update the stakeholder register and revise the stakeholder engagement plan.
-
D
Explain to the community members why they were not included as stakeholders for the project.
Reveal answer details
Close answer details
Question 46
Single choice
During the executing phase, a project manager is reviewing the issue log and finds there are outstanding high-priority issues that are still open. Most of the open issues require effort from external domain experts who are not on the project team. What should the project manager do?
-
A
Ask the issue reporter to close the issues, because there are no project team members who have the required domain knowledge.
-
B
Review the open issues with the issue reporter and issue a change request to hire an external domain expert.
-
C
Request that the project team members learn the required domain knowledge and resolve the open issues in a short time.
-
D
Reduce the project scope to ensure that the project team has the knowledge to deliver the system on schedule.
Reveal answer details
Close answer details
Question 47
Single choice
During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is concerned about working overtime. What should the project manager do to motivate the team?
-
A
Negotiate with the client to reduce the changes in requirements.
-
B
Crash the project schedule to ensure completion on time.
-
C
Introduce team-building activities to improve team performance.
-
D
Meet with the team members to review their roles and responsibilities.
Reveal answer details
Close answer details
Question 48
Single choice
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance. What should the senior project manager do now?
-
A
Use interpersonal skills to expedite the issue.
-
B
Send a gentle reminder to the technical service team.
-
C
Update the issue log with the status and priority.
-
D
Issue a formal warning to the technical service team.
Reveal answer details
Close answer details
Question 49
Single choice
A client's company announces a reorganization, which includes changes in the senior management involved in the project. The new project sponsor is asking to put the project on hold until they review the scope. What should the project manager do next?
-
A
Wait for a new project scope from the new project sponsor
-
B
Discuss the requirements and update the project management plan with the new sponsor
-
C
Discuss the issue with the project team and update the project management plan
-
D
Amend the risk register and provide suggested mitigation strategies
Reveal answer details
Close answer details
DRAG DROP A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts. Match the following common terms with their explanations that evaluate the buffers or constraints. 
Reveal answer details
Close answer details
Question 51
Single choice
A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification is received from the local community demanding that the project be stopped. What should the project manager do first?
-
A
Meet with project stakeholders to define a mitigation plan.
-
B
Register the issue and escalate it to the project sponsor.
-
C
Estimate the cost of changing the project location.
-
D
Execute the contingency plan defined in the risk management plan.
Reveal answer details
Close answer details
Question 52
Single choice
A project manager notices that a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?
-
A
Increase the sprint duration to accommodate the additional work.
-
B
Conduct a root cause analysis before addressing the issue.
-
C
Escalate the issue to the stakeholder's functional manager.
-
D
Cancel the one-on-one sessions and obtain the information via email.
Reveal answer details
Close answer details
Question 53
Single choice
A team member is frustrated, thinking that their performance is below average since they have not completed as many items as other team members. The team member has become negative and disengaged, bringing team collaboration and productivity down. What should the project manager do to increase the team's performance?
-
A
Meet with the team members and highlight individual contributions to encourage competition among the team.
-
B
Reiterate to the team that everyone is an important part of the team and performance is a team measurement, not an individual measurement.
-
C
Create a visual board to include the individual team members' performance levels so the team members can see all the contributions.
-
D
Speak to the team lead to identify ways to keep the team performing independently and individually address the team member's concerns.
Reveal answer details
Close answer details
Question 54
Single choice
A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members. The project manager tells the new team member to align with the team's principles and arrive on time. What kind of conflict resolution did the project manager apply in this situation?
-
A
-
B
-
C
Collaborate/problem solve
-
D
Reveal answer details
Close answer details
Question 55
Single choice
A project manager sent the first communication about the project management plan to the team. The next day, two field engineers were asking about their roles and the project schedule. What should the project manager have done?
-
A
Confirmed that the communication was understood and solicited feedback from the team
-
B
Sent the roles and responsibilities matrix along with the project management plan
-
C
Discussed the roles with the managers to help explain them to their team members
-
D
Briefed each team member on their roles before sending the project management plan
Reveal answer details
Close answer details
Question 56
Single choice
The vendor just informed the project manager that an item will not be delivered as scheduled due to a manufacturing error. This will impact the delivery timeline of the project as there are dependencies to the completion of this item delivery. What action should the project manager take?
-
A
Contact the vendor and insist on the agreed timeline since any item delay will affect the overall project.
-
B
Agree with the vendor on a revised timeline, document the issue, and identify tasks to finish while awaiting delivery.
-
C
Ensure this is documented as an issue and wait until the vendor delivers the item before progressing with any further tasks.
-
D
Ensure that the vendor is removed from the vendor management list to avoid working with them in the future.
Reveal answer details
Close answer details
Correct answerB
ExplanationThe correct answer is B because the scenario requires disciplined procurement and supplier management rather than an immediate, informal, or purely administrative reaction. The selected response - B. Agree with the vendor on a revised timeline, document the issue, and identify tasks to finish while awaiting delivery. -directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to assess supplier capability, contract impact, cost, quality, schedule, and available alternatives before committing project resources. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK(R) Guide Eighth Edition topics: process, procurement and supplier management, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.
Question 57
Single choice
A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day. What should the project manager do first?
-
A
Continue the project while trying to obtain the permit.
-
B
Update the risk management plan.
-
C
Review lessons learned from previous projects.
-
D
Obtain the permits before continuing the build.
Reveal answer details
Close answer details
Question 58
Single choice
A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has been working on this project for 6 months, and the morale of the team is low due to the schedule. What can the project manager do to motivate the team?
-
A
Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.
-
B
Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.
-
C
Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.
-
D
Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.
Reveal answer details
Close answer details
Question 59
Single choice
During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating. As a result, lots of misunderstandings occurred. What should the project manager do to address this issue?
-
A
Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates
-
B
Check the ground rules of the meeting to review the initial agreement with the team members
-
C
Identify one team representative to speak up during the daily meeting and share the team updates
-
D
Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak
Reveal answer details
Close answer details
Question 60
Single choice
A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform. What should the project manager do?
-
A
Use an agile approach and engage a vendor that delivered well in a previous organization.
-
B
Consult the product owner and engage a vendor that is recommended by them.
-
C
Consult the development team and engage a vendor that is recommended by them.
-
D
Use a formal approach using procurement policies, procedures, forms, and work instructions.
Reveal answer details
Close answer details
Question 61
Single choice
A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide. What should the project manager do?
-
A
Invite the sales manager to the next sprint meeting to clarify requirements.
-
B
Create a new item in the sprint backlog to determine the appropriate algorithm.
-
C
Ask the scrum master to choose an algorithm based on the pros and cons of each option.
-
D
Request a meeting with the product owner to help clarify the user story.
Reveal answer details
Close answer details
Question 62
Single choice
A project manager is assigned to a project. The project schedule and costs are tight, and the project manager determined that there is a lack of resources to deliver this project. What should the project manager do?
-
A
Identify the resource requirements and communicate them to the stakeholders seeking resources.
-
B
Update the risk register noting that, due to the lack of available resources, the project is likely to be delayed.
-
C
Define the work breakdown structure (WBS), identify the resource gaps, and reduce project management activities.
-
D
Formalize a scope change request with the stakeholders to adjust the project scope with the available resources.
Reveal answer details
Close answer details
Question 63
Single choice
Company A has a culture of adhering to policies and procedures. A project manager is applying an agile approach to their in-house software development project, but even with training, they are still unable to deliver efficiently. What should the project manager do first to improve this situation?
-
A
Empower and coach the team members to focus on project delivery results.
-
B
Identify key team members who can influence others to contribute efficiently.
-
C
Follow company procedures and retrain team members on the agile approach.
-
D
Ask company management to delay the project and grant it additional time.
Reveal answer details
Close answer details
Question 64
Single choice
An ongoing project is facing a challenging situation in which the customer is not satisfied. The team is new to agile development, communicates frequently with the customer, and provides regular status reports. What should the project lead do to satisfy the customer?
-
A
Reduce frequent communication and improve the status report format to include team progress.
-
B
Schedule a meeting with the customer and explain that the team is new to agile and that the situation will improve.
-
C
Review the situation with the customer and make the required adjustments with the team.
-
D
Review project progress with the customer and modify the frequency of sprint reviews.
Reveal answer details
Close answer details
Question 65
Single choice
A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date. What should the project manager do to manage such a situation for upcoming phases?
-
A
Revise the project schedule to accommodate fixing discovered issues.
-
B
Ensure customer validation occurs more frequently during the life cycle of the project.
-
C
Review the customer validation team's test plan early in the life cycle.
-
D
Ask the project team to increase unit testing of the deliverables.
Reveal answer details
Close answer details
Question 66
Single choice
During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output. What should the project manager do first?
-
A
Assign the work based on the skill sets of team members.
-
B
Request feedback from stakeholders about the quality delivery.
-
C
Assign the work in consultation with the functional manager.
-
D
Discuss this with the team and review the quality process.
Reveal answer details
Close answer details
Question 67
Single choice
The portfolio management office wants to cut costs by suspending some ongoing projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio management office has not backed down on their plan. What should the project manager do to continue the project?
-
A
Meet with the project team and revise the project goals.
-
B
Update the project charter to make it align with organizational strategy.
-
C
Demonstrate the project alignment to the organizational strategy.
-
D
Escalate the issue with the project sponsor to request support.
Reveal answer details
Close answer details
Question 68
Single choice
A project is in its fourth iteration out of eight, with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable that is not visible in the status report. What should the project manager do?
-
A
Include the deliverable in the status report and resend it to the stakeholder.
-
B
Invite the stakeholder to the next iteration review.
-
C
Invite the stakeholder to the next daily meeting.
-
D
Schedule a meeting with the stakeholder to review the status report.
Reveal answer details
Close answer details
Question 69
Single choice
An agile project in progress has a large number of blocked items and the project manager does not have visibility on the underlying issues. What should the project manager do to allow transparency and remove the blockers?
-
A
Create a shared kanban board for the team to have visibility of the items.
-
B
Hold a war room meeting with relevant people to address the blockers.
-
C
Change the project status to "on hold" to inform the sponsor about the blockers.
-
D
Conduct a retrospective meeting to gain visibility on what is happening.
Reveal answer details
Close answer details
Correct answerA
ExplanationThe correct answer is A because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response - A. Create a shared kanban board for the team to have visibility of the items. - directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK(R) Guide Eighth Edition topics: process, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.
Question 70
Single choice
The project manager of a globally dispersed team evaluates the organization's current virtual engagement tools and strategies. A couple of the remote team members are not participating effectively in virtual meetings. Which action should the project manager take to improve remote engagement?
-
A
Implement a new suite of collaboration tools to provide various communication options for the team.
-
B
Organize an in-person, team-building event to improve team engagement and communication.
-
C
Schedule one-on-one meetings with the team members to understand their specific needs and challenges.
-
D
Survey all team members to identify common issues with virtual engagement and address them systematically.
Reveal answer details
Close answer details
Question 71
Single choice
A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style. Which landscape describes the project environment?
-
A
High accountability, little authority
-
B
Good roadmaps, little accountability
-
C
Available resources, bad roadmaps
-
D
Enough authority, insufficient resources
Reveal answer details
Close answer details
Question 72
Single choice
What should an agile lead do lo ensure their team is set up for success?
-
A
Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level
-
B
Schedule sprint meetings and coaching sessions to discuss project-related information
-
C
Plan quarterly informal meetings or team bonding sessions to encourage the team to work together
-
D
Document team tasks and challenges in order to understand when to step in and help a member of the team
Reveal answer details
Close answer details
Question 73
Single choice
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to move its go-live date. What should the project manager do next?
-
A
Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.
-
B
Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.
-
C
Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.
-
D
Ask the sponsor to start a new project to support the existing project and help it meet the original time line.
Reveal answer details
Close answer details
Question 74
Single choice
A project manager has been asked for performance feedback regarding one of the team members. The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance. What should the project manager do next?
-
A
Evaluate demonstrated task accountability
-
B
Determine the appropriate approach
-
C
Analyze team member influence
-
D
Identify levels of decision-making authority
Reveal answer details
Close answer details
Question 75
Single choice
A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects. Which tool should the project manager use for this purpose?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 76
Single choice
A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not. What should the project manager do?
-
A
Conduct a performance review and define and document the goals for the team member.
-
B
Clarify decisions and request that the project team follows the project manager's decisions.
-
C
Understand what the team member wants and find possible opportunities to address it.
-
D
Remove existing ground rules and create new ground rules that support the project manager.
Reveal answer details
Close answer details
Question 77
Single choice
Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements. What should the project manager do to prevent this from happening again?
-
A
Review the risk impact of quality nonconformance.
-
B
Review the communications management plan.
-
C
Revise the quality management plan.
-
D
Revise the product acceptance specifications.
Reveal answer details
Close answer details
Question 78
Single choice
In an agile environment, a project is in iteration four out of six. A team member leaves the company with no replacement. What should the project manager do?
-
A
Update the issue log and refer to the resource management plan to address the situation.
-
B
Ask the team to do extra work to fulfill the project commitment.
-
C
Reduce the project scope and inform the stakeholders.
-
D
Ask the sponsor for an experienced team member from the company to help the project team.
Reveal answer details
Close answer details
Question 79
Single choice
An agile team recently started working on a project for a financial institution. The project sponsor is concerned that an agile approach will not provide enough support for the organization's compliance standards. In order to mitigate this risk and avoid problems, what should the project manager do?
-
A
Propose using a compliance review board that will be responsible for approving all product features prior to their release to the public.
-
B
Liaison with the compliance group, making them responsible for understanding the requirements and keeping them prioritized in the backlog.
-
C
Meet with the compliance team and make sure that their requirements are covered in the definition of done (DoD) for each story.
-
D
Ensure that the peer review process also covers compliance requirements, creating a second layer of security for the project.
Reveal answer details
Close answer details
Question 80
Single choice
A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain. When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?
-
A
-
B
Collaborative discussions
-
C
Workshops for risk avoidance
-
D
Interview with the project champion
Reveal answer details
Close answer details
Question 81
Single choice
There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project. How should the project manager handle this situation?
-
A
Counsel both team members and caution them with a final warning.
-
B
Escalate the issue to the human resources (HR) manager before a larger problem develops.
-
C
Help cultivate self-awareness between the two team members through emotional intelligence (El).
-
D
Relocate the two project team members into different project teams.
Reveal answer details
Close answer details
Question 82
Single choice
During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment. What type of analysis should the project lead have conducted to avoid this situation?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 83
Single choice
A project manager is managing a project which has a very complex and long execution period. Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework. The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework. What should the project manager do first?
-
A
Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them
-
B
Create a report based on the work breakdown structure (WBS) and update it on a regular basis.
-
C
Use the same benefits tracking process from the last predictive project and add this to the monthly status report
-
D
Research which templates of reports were used the most for this framework and incorporate them into the project
Reveal answer details
Close answer details
Question 84
Single choice
A project manager is leading an important development project. A key deliverable has been completed but does not meet the quality standards defined in the quality management plan. What should the project manager do?
-
A
Return the deliverable and ensure that the reworked deliverable meets the quality standards.
-
B
Approve the deliverable because it will not affect the project's overall quality standard.
-
C
Accept the deliverable and instruct the team to continue working without reporting the issue.
-
D
Adjust the quality standards to align them with the deliverable's current quality level.
Reveal answer details
Close answer details
Correct answerA
ExplanationThe completed deliverable fails the quality standards established in the quality management plan, so it should not be accepted or passed forward. The project manager should return it for correction and verify that the reworked deliverable satisfies the approved quality requirements and acceptance criteria. Approving a known nonconforming deliverable undermines governance and may transfer defects to downstream work, increasing cost, schedule delay, and customer dissatisfaction. Adjusting the standards merely to match poor output is also inappropriate unless an authorized change is justified through formal governance. Quality control requires inspecting results, identifying nonconformity, documenting defects, performing rework or corrective action, and confirming compliance before acceptance. The selected response protects fitness for use, prevents defect propagation, and maintains the integrity of the project's approved quality baseline.
Question 85
Single choice
On a transformational project, the project manager is confronted with resistance from the stakeholders. To overcome this and gain acceptance of the change, what should the project manager do first?
-
A
Escalate the issue to the project sponsor.
-
B
Review the stakeholder engagement plan.
-
C
-
D
Neutralize the negative stakeholders.
Reveal answer details
Close answer details
Question 86
Single choice
An agile project is in its early iterations, but the project manager already realizes that more resources will be needed to achieve the expected time lines. There are no internal resources available. What vendor strategy should the project manager use to maximize project delivery?
-
A
Use compression techniques to break down the scope and assign the scope pieces to different vendors with a fixed-price contract.
-
B
Use the contingency budget for hiring additional vendor resources to mitigate any project risk.
-
C
C. Engage in a time and materials (T&M) contract and hire a local vendor to support development.
-
D
Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.
Reveal answer details
Close answer details
Question 87
Single choice
A project steering committee meeting was arranged to approve a milestone of a project within two weeks. The project manager is informed that a new project executive will take over the project. What should the project manager do first?
-
A
Assess the risks with the team members.
-
B
Submit a change request to the change control board (CCB).
-
C
Evaluate the project impact and seek additional funding if necessary.
-
D
Brief the new stakeholders on the current project status.
Reveal answer details
Close answer details
Question 88
Single choice
In an agile team, some of the team members are coming forward to ask for more autonomy on the project. What should the project manager do in this situation?
-
A
Encourage the team members to make decisions.
-
B
Discourage them as conflicts may be created.
-
C
Encourage the team lead to make decisions.
-
D
Discourage this request, as it is for the management team.
Reveal answer details
Close answer details
Question 89
Single choice
A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?
-
A
The communications management plan was not used by all stakeholders.
-
B
Organizational assets were not available to back the rationale.
-
C
Relative estimation by the team resulted in two estimates.
-
D
The use of the Monte Carlo method can result in different estimations.
Reveal answer details
Close answer details
Question 90
Single choice
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders. The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts, which are listed on the project risk matrix. What should the project manager do with regard to community engagement in this situation?
-
A
Build channels to extend communication efforts to the local community.
-
B
Focus on the sideward stakeholders only and let the organization manage the community.
-
C
Use the city administration to address communication with the community.
-
D
Include the local union representative in the high-power, high-impact stakeholder group.
Reveal answer details
Close answer details
Question 91
Single choice
Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?
-
A
Evaluate the impact of skipping the quality check for the deliverable.
-
B
Seek approval from the sponsor on an extension of the project schedule.
-
C
Seek approval from the quality board to skip the quality check.
-
D
Ask the team member to work overtime to complete the quality check.
Reveal answer details
Close answer details
Question 92
Single choice
A project team has been formed, and the tasks have been assigned to each team member. All team members have agreed to follow a hybrid project approach. What should the project manager do to ensure the team performs as an organized unit?
-
A
Advise the team to adjust their work habits and behaviors to allow for better conflict resolution.
-
B
Call a team meeting to discuss team members' strengths and weaknesses.
-
C
Establish rules and regulations for team members with consequences if the goals are not reached
-
D
Establish team behavior and develop an understating of how to work together
Reveal answer details
Close answer details
Question 93
Single choice
A project has recently completed its production go-live, meeting the project's completion requirements in accordance with the scope document. However, the customer has been requesting a number of significant project enhancements. How should the project manager address the customer's requests?
-
A
Inform the customer that the project scope is completed and that further enhancements will require the initiation of a new project.
-
B
Tell the client that any extra work will require new scoping and pricing before the team can start additional enhancements.
-
C
Adjust the project completion requirements to the proposed enhancements and inform the project team of the additional work.
-
D
Explain to the customer that the project has been completed and enhancements will follow the change management process.
Reveal answer details
Close answer details
Question 94
Single choice
A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly. This uncertainty from the junior engineers is now slowing progress. What should the project manager do?
-
A
Update the risk register to reflect the possible impact of the projects slower progress.
-
B
Ensure the junior engineers make decisions within a certain responsibility level and commit to it.
-
C
Remove the junior engineers from any decision-making activity until further trained.
-
D
Pair senior engineers to shadow the junior engineers and correct them throughout.
Reveal answer details
Close answer details
Question 95
Single choice
A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager discovers that one of the remote team members, who puts a lot of effort into delivering the project, has confided in an on-site team member. The remote team member feels they are not being adequately rewarded and recognized for their job. What should the project manager do?
-
A
Inform the human resource (HR) manager of this situation and ensure this news does not spread.
-
B
Make arrangements with the resource's functional manager to relocate the team member to another existing project.
-
C
Send a copy of the engagement contract to the remote ber and indicate that the team member is entitled to what is included in the contract.
-
D
Engage the remote team member, empathize with them, and let them know their contribution is appreciated regardless of their remote work status.
Reveal answer details
Close answer details
Question 96
Single choice
A project to develop a new service is initiated by a telecommunications operator. The project management plan has been developed, approved, and shared with the respective stakeholders. What should the project manager do next?
-
A
Define deliverables, activities, and scheduling information.
-
B
Estimate activity durations and list resource requirements.
-
C
Incorporate the project's scope baseline into the scope statement.
-
D
Start executing the work packages according to the plan.
Reveal answer details
Close answer details
Question 97
Single choice
A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution. What should the project manager do first?
-
A
Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.
-
B
Decline the request politely since the issue, although critical, is not the responsibility of the project team.
-
C
Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.
-
D
Inform the customer that they should contact the sales manager and submit a formal request for a quote.
Reveal answer details
Close answer details
Question 98
Single choice
An agile team recently finished a product that met stakeholder expectations. However, a subsequent audit revealed that the product does not comply with local regulations. The team lead learns the team focused on the functions of the product and not the regulatory issues. What should the team lead do differently for the next project?
-
A
Remind the project team that they should collect requirements from all stakeholders.
-
B
Coach the team to solicit nonfunctional requirements in addition to functional requirements.
-
C
Instruct the product owner to revise the definition of done (DoD) during the sprint review meeting.
-
D
Conduct daily meetings to review the functional and nonfunctional requirements.
Reveal answer details
Close answer details
Correct answerB
ExplanationThe correct answer is B because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response - B. Coach the team to solicit nonfunctional requirements in addition to functional requirements. - directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK(R) Guide Eighth Edition topics: process, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.
Question 99
Single choice
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next? 
-
A
Continue with the sprint as the progress shows buffers for potential interruptions.
-
B
Ask the product owner if some low-priority stories could be cut from the sprint.
-
C
Continue with the sprint work as planned and keep monitoring.
-
D
Ask the project team to select any additional stories as they have additional capacity than planned.
Reveal answer details
Close answer details
Question 100
Single choice
A project manager is leading a project that is implementing an assembly line. During the quality review meeting, a team member reports an issue stating that the product being developed has discrepancies with the one requested by the customer. What should the project manager do?
-
A
Ensure the current solution is in place to enable future usability.
-
B
Run a root cause analysis to identify the quality breach and update the quality management plan.
-
C
Check that the product meets the requirements established by the customer.
-
D
Make a proposal of new specifications and submit it to the customer for approval.
Reveal answer details
Close answer details
|