On an agile project, some of the development team is struggling to understand how the tasks and user stories fit into the overall product.
How should this be addressed?
Reveal answer details Close answer details
Correct answerD
PMI · PMI-ACP
Preview real exam questions, verified answers and available explanations before choosing a study plan.
|
Single choice
On an agile project, some of the development team is struggling to understand how the tasks and user stories fit into the overall product. How should this be addressed? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which of the following is an example of an information radiator? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which tool allows the Product Owner to focus on providing the greatest value and Return on Investment (ROI) to the organization? Reveal answer details Close answer detailsCorrect answerB
Single choice
The ___________ the technical debt means the ________ the intrinsic quality? Reveal answer details Close answer detailsCorrect answerA
Single choice
Stakeholders have conflicting requirements, and the product owner is struggling to decide which user stories to write. What should the product owner do? Reveal answer details Close answer detailsCorrect answerD
Single choice
The project lead of a newly created agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery. What should the project lead do to address the gaps and develop a high-performing team? Reveal answer details Close answer detailsCorrect answerC
Single choice
The trend of work remaining across time in a Sprint, a release, or a product, with work remaining tracked on the vertical axis and the time periods tracked on the horizontal axis is called a ____________. Reveal answer details Close answer detailsCorrect answerA
Single choice
An infrastructure team had to revamp so downstream channels could consume data from the data lake, thereby improving operational efficiency for the end customers. Which primary components should the product manager consider while plotting performance and dependencies on the product roadmap? Reveal answer details Close answer detailsCorrect answerD
Single choice
What Scrum event or artifact supports daily inspection and adaptation? Reveal answer details Close answer detailsCorrect answerD
Single choice
An agile team notices that the same problems continue to occur during multiple iterations. Several team members have suggestions to fix the problem. What is the proper agile approach to handle this? Reveal answer details Close answer detailsCorrect answerD
Single choice
Pareto Analysis is the exercise of determining what 40% of functionality can be delivered with 60% of the effort. Reveal answer details Close answer detailsCorrect answerB
Single choice
A visual control used in Lean software development to represent the velocity of business solutions delivered over time is a: Reveal answer details Close answer detailsCorrect answerA
Single choice
The Agile artifact that describes the incremental nature of how a product will be built and delivered over time, along with the important factors that drive each individual release is called: Reveal answer details Close answer detailsCorrect answerC
Single choice
A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project deliverables could not be completed on time. How should the project team improve during their retrospective for future implementations? Reveal answer details Close answer detailsCorrect answerB
Multiple choice
Extreme Programming (XP) includes which of the following practices? (Choose three.) Reveal answer details Close answer detailsCorrect answersA, B, D
Hotspot
HOTSPOT Organizations that implement agile project management focus on upgrading existing products and services through cost reductions, time savings, or quality enhancements for existing customers (i.e., operational agility). ![]() Reveal answer details Close answer details![]()
Single choice
Agile project management and product development use several types of documents specific to each Reveal answer details Close answer detailsCorrect answerA
Single choice
Based upon this Burndown chart, is this project ahead of schedule or behind schedule? ![]() Reveal answer details Close answer detailsCorrect answerB
Single choice
An agile team wants to collectively determine a project's size. What will the team be doing if they use the planning poker technique to accomplish this? Reveal answer details Close answer detailsCorrect answerD
Single choice
An executive sponsor of a new scrum team actively attends scrum ceremonies. How does this benefit the team? Reveal answer details Close answer detailsCorrect answerA
Single choice
An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track? Reveal answer details Close answer detailsCorrect answerD
Single choice
A team member starts discussing a project roadblock during a daily coordination meeting. The team discusses details of the impediment, which takes up most of the meeting time. What should the agile facilitator do? Reveal answer details Close answer detailsCorrect answerD
Single choice
What should a scrum master do when an agile team member is behind on their tasks? Reveal answer details Close answer detailsCorrect answerC
Single choice
Testing that often occurs between "Done" and "Done, Done" is: Reveal answer details Close answer detailsCorrect answerA
Single choice
In Agile risk management, a risk burndown chart is best used to: Reveal answer details Close answer detailsCorrect answerD
Single choice
A high-performance Agile team: Reveal answer details Close answer detailsCorrect answerC
Single choice
The primary purpose of a Sprint retrospective is for the team to: Reveal answer details Close answer detailsCorrect answerC
Single choice
Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective. What should the agile practitioner do? Reveal answer details Close answer detailsCorrect answerB
Single choice
Alistair Cockburn created the Crystal Family of Agile Methods, all of whose names contain colors of quartz crystals taken from geology. What two characteristics of an Agile project are used to determine the color of the Crystal method? Reveal answer details Close answer detailsCorrect answerD
Single choice
A newly formed development team experienced difficulty with accurately estimating product backlog items. What should the team do to improve the accuracy of their estimates? Reveal answer details Close answer detailsCorrect answerB
Single choice
An executive notices a kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do? Reveal answer details Close answer detailsCorrect answerC
Single choice
Technical debt is the total amount of less-than perfect __________ in your project. Reveal answer details Close answer detailsCorrect answerB
Single choice
During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do? Reveal answer details Close answer detailsCorrect answerD
Single choice
The team is derailed by a demand from a senior manager unrelated to the project. How does the agile coach help the team? Reveal answer details Close answer detailsCorrect answerD
Single choice
Traditional project management uses requirement decomposition. This can be comparable to____________of Agile User Stories. Reveal answer details Close answer detailsCorrect answerC
Single choice
A project team's standups often run over the allotted time as members attempt to resolve issues. With a large team, this is leading to productivity impacts and bringing complaints from some members that the meetings are wasting their time when they are not directly involved in an issue's resolution. How can the project leader help to manage the team's time? Reveal answer details Close answer detailsCorrect answerD
Single choice
What is a Japanese term used in Lean software development is an activity that is wasteful, unproductive, and doesn't add value? Reveal answer details Close answer detailsCorrect answerC
Single choice
When an Agile project team receives an "emergency request" during an iteration, which is the best first step that the Agile project manager should take? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following is an example of a visual aid used in Lean-Agile software development? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the seven principles of software development is best intended to solve the problem of inventories causing hidden errors in the process? Reveal answer details Close answer detailsCorrect answerD
Single choice
A new agile team member notices that the team's current process involves excessive documentation. What should the new team member do? Reveal answer details Close answer detailsCorrect answerA
Single choice
A project is to be started with a team of nine existing and nine new members. The scrum master feels that the team is too large and wants to break it into three teams. The scrum master sets a constraint that each team have an equal number of existing team members for knowledge sharing and experience. What should the scrum master do to accomplish this? Reveal answer details Close answer detailsCorrect answerC
Single choice
While planning, what prioritization factors need to be considered for a minimally marketable feature (MMF)? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following is NOT a metric that measures the performance of DevOps in Agile? Reveal answer details Close answer detailsCorrect answerD
Single choice
At the end of first iteration, the team finishes User Stories A, Band 50% of C. What is the team velocity? ![]() Reveal answer details Close answer detailsCorrect answerB
Single choice
In Pair Programming, one programmer is responsible for all the coding in an iteration then the programmer switch for the next iteration? Reveal answer details Close answer detailsCorrect answerB
Single choice
A senior team member feels underutilized. What should the agile practitioner do? Reveal answer details Close answer detailsCorrect answerC
Single choice
A new agile team is forming to address a high-priority project. Team members are dispersed over a wide geographic area. The scrum master and the team are currently defining their working agreement. What should be part of the working agreement for a dispersed team? Reveal answer details Close answer detailsCorrect answerB
Single choice
Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing. How should the project manager explain why this is not the forum to ask these questions? Reveal answer details Close answer detailsCorrect answerD
Single choice
An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity. What should the team do? Reveal answer details Close answer detailsCorrect answerD
Single choice
An organization is undergoing an agile transformation to improve its market position. Management wants minimal overhead in connection with the agile initiative and wants the agile teams to control the work in process (WIP) and ensure that iterations do not result in waste. Which approach should be used in this scenario? Reveal answer details Close answer detailsCorrect answerD
Single choice
Daily coordination meeting attendance has been declining recently. Those who attend have little to contribute outside of what they are currently working on. The project manager met with the team to remind them of the importance of regular, face-to-face communication. The project team feels the daily coordination meetings are not adding value. What should the project manager do? Reveal answer details Close answer detailsCorrect answerD
Single choice
Osmotic communication is when team members obtain information from overhead conversations. Reveal answer details Close answer detailsCorrect answerA
Single choice
An agile coach is guiding a team across multiple locations. They need a united communication approach that involves task-oriented communications and discussion boards with effectiveness. Which method of communication would be most effective? Reveal answer details Close answer detailsCorrect answerB
Single choice
As user stories are developed, what should be done to record and update acceptance criteria? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following is NOT one of the 12 core practices of XP: Reveal answer details Close answer detailsCorrect answerD
Single choice
With multiple Scrum teams, you should have a separate product backlog. Reveal answer details Close answer detailsCorrect answerB
Single choice
A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status. ![]() How many sprints will be needed to complete the entire backlog? Reveal answer details Close answer detailsCorrect answerA
Single choice
During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them. What should have been done to avoid this? Reveal answer details Close answer detailsCorrect answerB
Single choice
Stakeholders are displeased with the latest release of a product's software. While most stakeholders attended every sprint review, they were otherwise largely uninvolved in the project. What should the agile practitioner have done to ensure stakeholder satisfaction? Reveal answer details Close answer detailsCorrect answerB
Single choice
During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval. Reveal answer details Close answer detailsCorrect answerB
Single choice
During iteration planning, it was determined that an epic should be decomposed. What was the determining factor? Reveal answer details Close answer detailsCorrect answerA
Single choice
The following is a picture of which of the following Information Radiators? ![]() Reveal answer details Close answer detailsCorrect answerC
Multiple choice
Prioritize from high to low the sequence of User Story development. Reveal answer details Close answer detailsCorrect answersA, B, C, D
Single choice
During a retrospective, the team agrees that they have limited competence in using a newly introduced tool. What should the team do? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which one is NOT a reason to perform a Spike? Reveal answer details Close answer detailsCorrect answerC
Single choice
A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals needs to happen at many levels in the company. What should the team lead do to improve decision quality and reduce the time required to make decisions? Reveal answer details Close answer detailsCorrect answerA
Single choice
At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised. How should this situation have been prevented? Reveal answer details Close answer detailsCorrect answerC
Single choice
Who is responsible for change management in Scrum projects? Reveal answer details Close answer detailsCorrect answerD
Single choice
An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the Scrum Master do? Reveal answer details Close answer detailsCorrect answerD
Single choice
An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work. What metrics should the team use to measure performance? Reveal answer details Close answer detailsCorrect answerA
Single choice
On an Agile team, the project leader works to remove impediments from blocking the team's progress. Reveal answer details Close answer detailsCorrect answerA
Single choice
A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner? Reveal answer details Close answer detailsCorrect answerB
Single choice
A senior executive contacted an agile lead about starting an agile project to solve a problem for the human resources (HR) department of a company. The project idea is not clear and no backlog has been developed. How should the agile lead start the project? Reveal answer details Close answer detailsCorrect answerB
Single choice
Business stakeholders of an agile project frequently skip the review meetings. What should the agile practitioner do? Reveal answer details Close answer detailsCorrect answerD
Single choice
An agile team lead noticed their team's velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members. What should the agile team lead do at the end of this iteration? Reveal answer details Close answer detailsCorrect answerB
Drag & drop
DRAG DROP How do you read a burndown bar chart? Match the phrases below to create instructions. ![]() Reveal answer details Close answer details![]()
Single choice
Who is responsible for determining the business value of each feature? Reveal answer details Close answer detailsCorrect answerA
Single choice
An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date. How should the agile coach address this change? Reveal answer details Close answer detailsCorrect answerC
Drag & drop
DRAG DROP What is the order the hierarchy of product definition? ![]() Reveal answer details Close answer details![]()
Single choice
Project managers use velocity to determine: Reveal answer details Close answer detailsCorrect answerA
Single choice
One of the main stakeholders of a project is new to Scrum. The stakeholder asks what to expect in the sprint retrospective. How should the product owner respond? Reveal answer details Close answer detailsCorrect answerD
Single choice
An agile practitioner wants to ensure that stakeholders have current information about a project's progress. What should the agile practitioner do? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the following would be most likely to assist when a customer has difficulty prioritizing stories? Reveal answer details Close answer detailsCorrect answerA
Single choice
On a risk map or a risk heat map, the vertical and horizontal axes represent: Reveal answer details Close answer detailsCorrect answerB
Single choice
Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item. Which of the following should the agile project manager do? Reveal answer details Close answer detailsCorrect answerA
Single choice
During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight. What should the agile coach do? Reveal answer details Close answer detailsCorrect answerB
Single choice
During a review session, a customer representative is concerned that a story fails to satisfy the scope of work. However, the product owner declares that the scope of work is complete? What should be done with this story? Reveal answer details Close answer detailsCorrect answerA
Single choice
Since the last iteration, the team has grown from six members to 14 members. As a result, in the current iteration, the team room is crowded and uncomfortable during the team's daily standup. It takes the team longer than the ideal amount of time to complete their standup, which creates problems for the team's current schedule. Based on this information, the project manager should: Reveal answer details Close answer detailsCorrect answerD
Single choice
An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Reveal answer details Close answer detailsCorrect answerC
Single choice
A client states that a product is not being built as requested. How should the agile team address this? Reveal answer details Close answer detailsCorrect answerD
Single choice
An agile leader has been assigned to a project that involves significant technical complexity. What should the agile leader do to set the project up for success? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which is NOT a principle of Lean? Reveal answer details Close answer detailsCorrect answerB
Single choice
An executive requests information regarding a sprint status. What action should the product owner take? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following is a list of valid Agile project planning practices? Reveal answer details Close answer detailsCorrect answerA
Single choice
An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements. What should the team do next? Reveal answer details Close answer detailsCorrect answerD
Multiple choice
What is the sequence of Tuckman's stages of team formation and development progress? Reveal answer details Close answer detailsCorrect answersA, B, C, D
Single choice
No one, not even the Scrum Master, tells the development team how to build the product. Reveal answer details Close answer detailsCorrect answerA
Single choice
An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system. Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? Reveal answer details Close answer detailsCorrect answerA
Single choice
The most appropriate model for a geographically distributed project team is one in which the team is distributed across: Reveal answer details Close answer detailsCorrect answerA |