An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review. What should the program manager do next?
-
A
Assign resources to the schedule and report the revised delivery date to the project managers.
-
B
Work with the project managers to refine the project schedules and deliverables to align with the program milestones.
-
C
Revise the project schedules to meet the program schedule and communicate to stakeholders.
-
D
Integrate the project schedules into the program schedule and report the revised delivery date to the project managers.
Reveal answer details
Close answer details
You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
A program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced. The program manager will use the qualified seller list to do which of the following?
-
A
Plan a proposal evaluation system
-
B
Prepare the program procurement management plan
-
C
Perform the required program budget updates
-
D
Issue requests for proposals
Reveal answer details
Close answer details
Your company and a competing company have created a teaming agreement for an opportunity. Through this team agreement you and your competitor can complete a major program for a client. This is, technically, a risk response for both organizations. What type of risk response are you dealing with in this instance?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
You are the program manager for the HNY Corporation and you complete programs for other companies in your role. You have just been assigned a new program that is very similar to a recently completed program you did for your company. Management has asked you to create a cost estimate for the program so you base your current cost estimate on the recently finished program. What type of estimating technique have you used in this instance?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
During a program's definition phase, it is determined that the best approach for delivering the program's intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers. The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?
-
A
Make-or-buy decisions, alternatives analyses, approach to competition, and best mix of contract types
-
B
Requests for proposals (RFPs), proposal evaluation criteria, contract management, and best mix of contract types
-
C
RFPs, alternatives analyses, approach to competition, and requests for quotes (RFQs)
-
D
Make-or-buy decisions, proposal evaluation criteria, contract management, and RFQs
Reveal answer details
Close answer details
You are the program manager for your organization. Your current program, which has just been initiated, needs to launch several projects in order to create all of the benefits of the program. What document do you need to create in order to initiate the projects within your program?
-
A
-
B
-
C
-
D
Project preliminary scope statement
Reveal answer details
Close answer details
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B. This is an example of which of the following?
-
A
Program resource management planning
-
B
-
C
Resource interdependency management
-
D
Project resource planning
Reveal answer details
Close answer details
A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?
-
A
Certify contract completion
-
B
Conduct a procurement audit to review the procurement process
-
C
Assess all contracts to ensure all agreed conditions are met
-
D
Review contract management plan for completeness
Reveal answer details
Close answer details
Question 10
Single choice
An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However, the business team does not report to the IT program manager, and only two business team resources with the appropriate skills are available to complete the required program tasks. To address this issue, what should the IT program manager do next?
-
A
Schedule a meeting with the business team to discuss transferring the two business team resources to the IT team; update the program risk register to include risk mitigation steps.
-
B
Escalate the lack of commitment by the business team to the program steering committee; hire a new project resource to complete the required tasks; update the program risk register to include risk mitigation steps.
-
C
Review and clarify the business team's program roles and responsibilities; determine the schedule impact on benefits delivery; direct the IT project manager to meet with the business team to ensure dependencies are understood and that the appropriate resources can be made available.
-
D
Modify the program milestone dates to include a larger contingency; determine the impact on the project implementation date; update the benefits management plan.
Reveal answer details
Close answer details
Question 11
Single choice
You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario?
-
A
This is an example of a preventive action.
-
B
This is an example of team development.
-
C
This is an example of quality assurance.
-
D
This is an example of a corrective action.
Reveal answer details
Close answer details
Question 12
Single choice
You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this scenario?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 13
Single choice
A program manager initiates a developmental program. Significant resources and funding are required for early activities until the program cost and budget estimates are complete. What should the program manager do to understand the financial environment?
-
A
Map costs to the expected benefits realization.
-
B
Establish intermediate budget based on historical information.
-
C
Establish program financial framework.
-
D
Obtain intermediate funding from the executive sponsor.
Reveal answer details
Close answer details
Question 14
Single choice
Which of the following contract types is described in the statement below? "The seller is reimbursed for all allowable costs for performing the contract work, and receives a fixed payment calculated as a percentage for the initial estimated project costs."
-
A
Cost Plus Fixed Fee Contracts (CPFF)
-
B
Fixed Price Incentive Fee Contracts (FPIF)
-
C
Firm Fixed Price Contracts (FFP)
-
D
Cost Plus Incentive Fee Contracts (CPIF)
Reveal answer details
Close answer details
Question 15
Single choice
While setting up a program's infrastructure and plan, a program management team develops documents and processes that provide commonality and consistency throughout the program's components. What should the team also prepare, if not already provided by the organization's assets?
-
A
Breakdowns such as the program work breakdown structure (PWBS), component project milestones, and budgets that transform top-level planning into fragments relevant to the components
-
B
Industry standards that provide guidance to the component project managers on how to adapt their detailed planning to the program's master plan
-
C
Documents that enable level-adequate aggregation and consolidation of component/program information and forecasting
-
D
Files, filing structures, and templates for knowledge repositories that contain centrally stored and commonly maintained program data
Reveal answer details
Close answer details
Question 16
Single choice
You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?
-
A
Certificate of completion
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 17
Single choice
An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers. What should the program manager do first to obtain program approval?
-
A
Prepare the stakeholder engagement plan for approval by the program steering committee.
-
B
Analyze the business environment to identify key stakeholders, and then perform a stakeholder analysis.
-
C
Conduct a brainstorming session with the program team to identify and analyze external stakeholders.
-
D
Create a project-level stakeholder analysis, and then perform a high-level program stakeholder analysis.
Reveal answer details
Close answer details
Question 18
Single choice
You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 19
Single choice
A component project of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations. What should the program manager do next?
-
A
Reassign the component project manager to another component project or activity
-
B
Verify that the benefits were delivered and authorize component project closure
-
C
Conduct a program audit to confirm that the component project is complete
-
D
Keep the component project open until the program benefits are realized
Reveal answer details
Close answer details
Question 20
Single choice
A municipal agency manages a city's water and wastewater infrastructure. Its six-year capital improvement program (CIP) is approximately US$4 billion, and is used for such things as improving aging infrastructure, addressing regulatory requirements, and upgrading facilities. The mayor and key stakeholders are concerned because of yearly rate increases for residents. After receiving proposals from program managers for this key program, which is half of the current CIP, a program management team is hired and receives an approved business case. What should the project manager do next?
-
A
Discuss the program change and its challenges.
-
B
Create a program management plan.
-
C
Conduct a program performance analysis.
-
D
Develop a program charter.
Reveal answer details
Close answer details
Question 21
Single choice
Who prepares the statement of work (SOW) for external projects?
-
A
-
B
-
C
-
D
Chief Financial Officer (CFO)
Reveal answer details
Close answer details
Question 22
Single choice
The ____ quality assurance technique ensures continuous improvement of all processes.
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 23
Single choice
The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year. Where is this expectation documented?
-
A
Program quality standards
-
B
-
C
-
D
Benefits sustainment plan
Reveal answer details
Close answer details
Question 24
Single choice
A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process. How should the program manager handle this situation?
-
A
Review the final program outcome with the program sponsor
-
B
Prepare a program change request utilizing new board member input
-
C
Review the strategic plan and benefits management plan with the board
-
D
Present the final program status, costs, and schedule reports
Reveal answer details
Close answer details
Question 25
Multiple choice
Which of the following statements are true regarding program scope changes? (Choose three.)
-
A
Scope changes may originate from the stake holders.
-
B
Change requests for a particular project have to be approved by the project manager irrespective of their potential impact on multiple projects.
-
C
The program has a change control board that analyzes changes at the program level.
-
D
The change control process on a program is often hierarchical.
Reveal answer details
Close answer details
Question 26
Single choice
Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?
-
A
Resource breakdown structure
-
B
Resource management chart
-
C
Stakeholder analysis chart
-
D
Reveal answer details
Close answer details
Question 27
Multiple choice
Which of the following tools and techniques are parts of the Administer Program Procurements process? Each correct answer represents a complete solution. Choose all that apply.
-
A
-
B
-
C
Supplier performance review
-
D
Contract performance review
Reveal answer details
Close answer details
Question 28
Single choice
You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You know that there are three positive risks responses and three negative risk responses that each risk can have. Management asks you which risk response would be most appropriate for a large risk event if they wanted to hire a third-party to own the risk event for the program. What risk event is most appropriate?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 29
Single choice
You are the project manager for your organization and are working with the project stakeholders and the business analyst to define all of the deliverables the project is to create. The stakeholders would like the option of adding more deliverables later in the project and keeping the requirements somewhat open for changes. You explain to the business analyst that you need a set of requirements that define exactly what needs to be delivered for the project. What document are you trying to create in this early stage of the project?
-
A
Requirements technical documentation
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 30
Single choice
An organization supports both programs and projects for various industries. What is a portfolio?
-
A
A portfolio is the total amount of funds that have been invested in programs, projects, and operations.
-
B
A portfolio describes all of the monies that are invested in the organization.
-
C
A portfolio describes the organization of related projects, programs, and operations.
-
D
A portfolio describes any project or program within one industry or application areA.
Reveal answer details
Close answer details
Question 31
Single choice
You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 32
Single choice
What cost estimating approach uses the work breakdown structure to create a cost estimate?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 33
Single choice
A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST). What should the program manager update?
-
A
Program communications management plan
-
B
-
C
Stakeholder engagement plan
-
D
Reveal answer details
Close answer details
Question 34
Single choice
You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?
-
A
-
B
Law of Diminishing Returns
-
C
-
D
Reveal answer details
Close answer details
Question 35
Single choice
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits. Which of the following actions should the program manager take?
-
A
Focus on the internal stakeholders to ensure cost and schedule objectives are achieved.
-
B
Balance stakeholder needs through the use of trade-offs among the stakeholder groups.
-
C
Focus on the external stakeholders to ensure the intended benefits are achieved.
-
D
Conduct a stakeholder meeting to allow everyone to state their priorities.
Reveal answer details
Close answer details
Question 36
Single choice
Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?
-
A
Value-added change requests
-
B
-
C
Integrated change control
-
D
Reveal answer details
Close answer details
Question 37
Single choice
You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they've not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training. The cost of the training in this instance is known as which one of the following?
-
A
-
B
-
C
-
D
Cost of conformance quality
Reveal answer details
Close answer details
Question 38
Single choice
A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified. Key stakeholders for the program should include which of the following?
-
A
Potential customers, government regulatory agencies, and competitors
-
B
Project management office (PMO), third-party contractors, and agents
-
C
Local car dealers, factory workers, and corporate officers
-
D
Vice president of logistics, potential customers, and corporate executives
Reveal answer details
Close answer details
Question 39
Single choice
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder, but is unable to reach a compromise on the requirement. What should the program manager do first?
-
A
Meet with the program management office to update the benefits management plan
-
B
Meet with organization's strategic planning committee to obtain clarification
-
C
Meet with the program sponsor to address the issue
-
D
Meet the customer to determine if the stakeholder's requirement is valid
Reveal answer details
Close answer details
Question 40
Single choice
Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B's program manager has just advised that program B has been closed. What should program A's program manager update and review first with the stakeholders?
-
A
Benefits sustainment plan
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 41
Single choice
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention. What should be done with the identified potential risk?
-
A
Incorporate it into the risk register and perform a thorough analysis.
-
B
Mitigate the risk before it is incorporated into the risk management plan.
-
C
Document the risk in the program transition plan and identify it as a potential issue.
-
D
Document it in the issue log and immediately notify the steering committee.
Reveal answer details
Close answer details
Question 42
Single choice
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk. What should the program manager do to monitor and control the supplier?
-
A
Use expert judgment, and update the program procurement plan.
-
B
Seek stakeholder approval of program procurement management activities.
-
C
Examine performance reports, audits, and inspections.
-
D
Review proposal evaluation criteria, risk analyses, and mitigation strategies.
Reveal answer details
Close answer details
Question 43
Single choice
A company is rolling out an innovative program that includes new processes intended to define how the company will manage future programs. While program execution is going well, the program sponsor is concerned that the knowledge acquired needs to be reused for future programs. What should the program manager do to ensure that the knowledge acquired is captured efficiently?
-
A
Record lessons learned in the program management plan
-
B
Create training materials summarizing team experiences and lessons learned
-
C
Direct the project managers to create event logs to document their experiences and lessons learned
-
D
Organize review sessions after each program stage to document successes, issues, and lessons learned
Reveal answer details
Close answer details
Question 44
Single choice
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?
-
A
-
B
-
C
Vendor analysis requirements
-
D
Reveal answer details
Close answer details
Question 45
Single choice
How does a portfolio's collection of work differ from that of a program's collection of work?
-
A
Outcomes are interdependent
-
B
Benefits are achieved only when managed collectively
-
C
Components may be independent
-
D
Reveal answer details
Close answer details
Question 46
Single choice
There are five stages of team development. At which stage are there likely to be disagreements and struggle for roles in the program team?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 47
Single choice
You are the program manager for your organization and your team has reported on a new issue among your program stakeholders. You want to address this issue as soon as possible, but it will need to be studied and reviewed. You recommend that Shirley, one of your program team members, study the issue and present a few solutions in a week's time. What else should you do with the issue?
-
A
Determine the time and cost of researching the issue for resolution.
-
B
Record the issue in the issue log.
-
C
Document the issue in the lessons learned.
-
D
Communicate with the stakeholders that you are addressing the issue.
Reveal answer details
Close answer details
Question 48
Single choice
You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie?
-
A
A program is a collection of projects that work together to create one deliverable for the organization
-
B
A program is a collection of projects managed to gain benefits for the organization; the organization could not realize the benefits of the project if they were managed independently.
-
C
A program is a uniform set of goals that are too large to be managed as one independent project so the project is subdivided into multiple objectives led by multiple project managers and orchestrated by one program manager.
-
D
A program is a large collection of projects lead by a single project manager.
Reveal answer details
Close answer details
Question 49
Single choice
At the beginning of the second year of a five-year strategic cycle, the program management team attends a checkpoint session to review the state of the company's strategy. During the previous year, the company needed to comply with new government regulations that impacted this strategy. Based on this information, what should the program manager do?
-
A
Update the program management, benefits management, and risk management plans, and modify priorities and interdependencies.
-
B
Meet with stakeholders, and modify the program roadmap to comply with the new regulations and ensure strategic alignment.
-
C
Obtain stakeholder approval to stop or postpone programs that fail to comply with the new regulations, and modify the program roadmap.
-
D
Review resource capacity and capability, program priorities, and interdependencies, and create a change request to modify the program roadmap to ensure strategic alignment.
Reveal answer details
Close answer details
Question 50
Single choice
Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?
-
A
Stakeholder management plan
-
B
Communications management plan
-
C
Human resource management plan
-
D
Interface management plan
Reveal answer details
Close answer details
Question 51
Single choice
You have completed a project for a client at his facility. The project has lasted for 18 months and you have generated many reports, plans, change request forms, and other documents about the project work. What should you do with the project documentation?
-
A
Give it to the client for his information.
-
B
Destroy it, as this information is relevant to the client.
-
C
Archive it as part of your organization's process assets.
-
D
Leave it as is for the client to destroy or archive.
Reveal answer details
Close answer details
Question 52
Single choice
A company's marketing department fails an internal compliance audit. To comply with the auditor's remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented. What should the program manager do to ensure the success of the program?
-
A
Meet with the vice president of purchasing to discuss the risks associated with preselecting a solution before the requirements have been gathered
-
B
Host a kick-off meeting; request preliminary requirements from the marketing department; conduct a design session; present the steering committee with a solution that meets the requirements; and meet with interested vendors
-
C
Ask a senior marketing executive to act as the program sponsor and participate on the steering committee; require steering committee representation from the IT, legal, and other key departments; validate that the chosen solution meets the requirements
-
D
Initiate the program and begin a formal request for proposal (RFP) to validate the chosen solution and gain the confidence of the legal department
Reveal answer details
Close answer details
Question 53
Single choice
If a risk has a probability of 60 percent and an impact of -$57,000 what will the expected monetary value of the risk event be?
-
A
-
B
-
C
-
D
You will need to know the utility function of the organization to determine this.
Reveal answer details
Close answer details
Question 54
Single choice
You are the program manager for your program and are creating a communications management plan. Management wants you to address the type of communications based on the number of communication channels you'll have within the program. Currently there are 345 stakeholders in your program but next week you'll have 387 stakeholders. How many more communication channels will you have next week in your program?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 55
Single choice
A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components' strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools. Which of the following must be addressed?
-
A
Program performance monitoring and controlling
-
B
Program management information system (PMIS)
-
C
Program delivery management
-
D
Reveal answer details
Close answer details
Question 56
Single choice
Which of the following risk identification techniques is described in the statement below? "It is used to gather information where participants don't know each other nor do they have to be present at the same location."
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 57
Single choice
A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks. What should the program manager do next to address this risk?
-
A
Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.
-
B
Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register.
-
C
Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this.
-
D
Add the lack of skilled resources to facilitate the large number of change requests to the issue log.
Reveal answer details
Close answer details
Question 58
Single choice
Wan is the program manager for his organization. He has been hearing reports that some project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?
-
A
The schedule to complete the work will take longer.
-
B
The cost of the program and project will increase.
-
C
The risks of failure will increase.
-
D
The morale of the project managers will decline.
Reveal answer details
Close answer details
Question 59
Single choice
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set. If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?
-
A
Reduction in program quality
-
B
Degradation of program communications
-
C
Reduction in program risk
-
D
Slow down in program implementation
Reveal answer details
Close answer details
Question 60
Single choice
A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter?
-
A
Milestone dates, budget, and staff details that support it
-
B
Assumptions incorporated into the benefits management plan
-
C
Process within the organization that will be needed to deliver the product
-
D
Key decision makers or stakeholders in the program and their expectations and interests
Reveal answer details
Close answer details
Question 61
Single choice
You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?
-
A
Program requirements for resource competency levels
-
B
Structure of the program management team
-
C
Metrics and qualifications for program acceptance
-
D
Location of the program work
Reveal answer details
Close answer details
Question 62
Single choice
The program manager takes over a poorly performing program. After a review of the documentation and interviews with the program sponsor, stakeholders, and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent projects and components to meet the program's needs. What action should the program manager take to realign the program?
-
A
Assess the program schedule and determine how to maintain all projects and components within the program.
-
B
Discuss the situation with the program stakeholders and let them decide which projects to accelerate and which to close.
-
C
Discuss the situation with the program sponsor(s) and let the sponsor(s) make the decision as to which projects to accelerate and which to close.
-
D
Develop a change request to present to the governance board, accelerate some projects, close some projects, and reassign some resources.
Reveal answer details
Close answer details
Question 63
Single choice
A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released to the program team and developers to create new software called Beta. While the program manager prepares the program closure plan for Alpha, the program sponsor expresses concern about its support after program closure. What should the program manager do as part of Alpha's program closure plan?
-
A
Execute the transition plan, and include knowledge transfer to transition Alpha support to operations.
-
B
Keep the Alpha program open until support is no longer required, then execute program closure.
-
C
Adjust Alpha's exit criteria to ensure its support is included in the Beta program.
-
D
Document the program closure procedure to ensure that resources are released from Alpha to develop Beta.
Reveal answer details
Close answer details
Question 64
Single choice
A company is evaluating the implementation of enterprise resource planning (ERP) software. The program manager performs an analysis to confirm the program's feasibility. What other important step should the program manager complete?
-
A
Development of the program's vision statement
-
B
Review of strategic goals against any external environmental factors
-
C
Identification and documentation of the initial risks for ERP software implementation
-
D
Mapping of the financial benefits to the ERP software's functionality
Reveal answer details
Close answer details
Question 65
Single choice
You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 66
Single choice
A program is completed and the expected benefits are realized. Before executing the transition and closing of the program, what should the program manager do?
-
A
Create a final program report
-
B
Archive documents and lessons learned
-
C
Obtain approval from the program governance board to initiate program closure activities
-
D
Perform administrative and program management information system (PMIS) closure activities
Reveal answer details
Close answer details
Question 67
Single choice
A program manager, who reports to a company's CIO, is responsible for managing a strategic initiative program. During a program review meeting, the CIO informs the program manager about potential budget cuts that would impact program resources, and urges the program manager to begin delivering benefits more quickly to continue the program. What should the program manager do first?
-
A
Update the benefits management plan, and send it to stakeholders for review.
-
B
Document the impact on the program, then present the findings to the steering committee to determine next steps.
-
C
Conduct a risk assessment associated with an accelerated schedule, update the risk register, and request steering committee approval.
-
D
Revise the program schedule to adapt to an accelerated delivery of benefits, and present it to the steering committee for approval.
Reveal answer details
Close answer details
Question 68
Single choice
____ is the degree to which a set of inherent characteristics fulfills requirements.
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
|