You are a Project Manager in your organization who is managing a considerably huge budget project to develop new software. Considering the varied nature of your stakeholder group, you would like to put together a plan as to what information the stakeholders need, and how to provide that information. What is the document that you would need, and as part of which process group would you achieve this?
-
A
Project Management Plan, Planning Process Group
-
B
Project Management Plan, Initiating Process Group
-
C
Communications Management Plan, Execution Process group
-
D
Communications Management Plan, Planning Process Group
Reveal answer details
Close answer details
Question 2
Multiple choice
Which of the following are outputs of the Plan Quality process? Each correct answer represents a complete solution. Choose all that apply.
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
You are in a project to create a Website. Your project team has met a few times and you're working with them to develop the project's WBS. Jan, a marketing expert, is in disagreement with Larry over how the Website should function. Gary and Gina are in disagreement over who'll take the lead on the design of the software for the Website. Mark, Mary, and Martha are all bickering about the photo management approach for the Website's pictures. What stage of team development is your project team currently in?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don was to perform a risk audit, who would carry the risk in this scenario?
-
A
Jerry would because he is the hired contractor.
-
B
Don would because he is the project manager.
-
C
Don would because of the contract type.
-
D
Jerry would because of the contract type.
Reveal answer details
Close answer details
You work as a project manager for PassGuide Inc. You want to include a budget contingency to accommodate the risk of incurring unidentifiable but normally occurring costs within the defined scope. Which of the following processes will help you to accomplish the task?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Which of the following processes improves the competencies and interaction of the team?
-
A
-
B
-
C
Project human resource plan process
-
D
Reveal answer details
Close answer details
You work as a project manager for PassGuide Inc. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the ownership of the response?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
You work as a project manager for PassGuide Inc. You are using market risk, value at risk (VaR), historical simulation (HS), and extreme value theory (EVT) so as to analyze a portfolio and make forecasts of the likely losses that would be incurred for a variety of risks. Which of the following processes are you using to accomplish the task?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Which of the following techniques is described in the statement below? "It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid of any resource limitations by performing a forward and backward pass analysis through the schedule network."
-
A
-
B
-
C
-
D
Resource leveling heuristic
Reveal answer details
Close answer details
Question 10
Single choice
Which of the following quality costs determines, assesses, or audits products or services to assure conformance to quality standards and performance requirements?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 11
Single choice
You work as a project manager for PassGuide Inc. You are working on a construction project. You are compiling and reviewing the comments to draft deliverables prior to forwarding them to the contractor for incorporation into the final draft. You are responsible for communicating the changes to the reviewer who initially made the comments. Who among the following will be responsible for updating the draft deliverables and producing the final deliverables in the above scenario?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 12
Single choice
You work as a project manager for PassGuide Inc. You want to calculate the probability of loss due to cost overrun. Which of the following terms describes the above metric?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 13
Single choice
You work as a project manager for PassGuide Inc. Your project has a budget of $545,000 and is expected to last 12 months. You have identified several risk events and created risk response plans for your project. In which of the following process groups will you be able to implement risk response plans?
-
A
-
B
-
C
-
D
Monitoring and controlling
Reveal answer details
Close answer details
Question 14
Single choice
Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?
-
A
Project communications plan
-
B
-
C
Project contractual relationship with the vendor
-
D
Reveal answer details
Close answer details
Question 15
Single choice
In which of the following process groups is the project manager responsible for authorizing and applying organization resources to the subsequent project activities?
-
A
-
B
-
C
-
D
Monitoring and controlling
Reveal answer details
Close answer details
Question 16
Multiple choice
You work as a project manager for PassGuide Inc. You are in the project kickoff meeting. Which of the following documents are reviewed during the project kickoff meeting? Each correct answer represents a complete solution. Choose all that apply.
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 17
Single choice
Which of the following components of EVA is described in the statement below? "It is a measure of how much of the project value has been earned so far through completed work, that is, the budgeted cost of the work that has been performed through the project status date."
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 18
Single choice
You work as a Project Manager for PassGuide Inc. You are developing the schedule for your project. Your project deals with the construction of a new building for PassGuide Inc. You want to break the project into small, individual, and manageable components. Which of the following tasks will you perform in the above scenario?
-
A
-
B
-
C
Create an activity diagram.
-
D
Reveal answer details
Close answer details
Question 19
Single choice
Which of the following is built by aggregating the costs of the individual work elements and then joining them at time intervals where meaningful actual cost information will be available?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 20
Single choice
You are the project manager for the HGQ Project. You and the project team are currently working on the Identify Risks process. When does this project typically happen in a project?
-
A
-
B
During project initiation
-
C
Throughout the entire project
-
D
During project monitoring and controlling
Reveal answer details
Close answer details
Question 21
Single choice
Which of the following is a measure of progress achieved compared to progress planned on a project?
-
A
-
B
Schedule performance index
-
C
-
D
Reveal answer details
Close answer details
Question 22
Single choice
In which of the following contract types, the seller is reimbursed for all allowable costs for performing the contract work and receives a fixed fee payment which is calculated as a percentage of the initial estimated project costs?
-
A
Communications Management Plan, Execution Process group
-
B
Communications Management Plan, Planning Process Group
-
C
Project Management Plan, Planning Process Group
-
D
Project Management Plan, Initiating Process Group
Reveal answer details
Close answer details
Question 23
Multiple choice
Which of the following are outputs of the Perform Quality Control process? Each correct answer represents a complete solution. Choose all that apply.
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 24
Single choice
In which of the following process groups is the project manager responsible for authorizing and applying organization resources to the subsequent project activities?
-
A
-
B
-
C
-
D
Monitoring and controlling
Reveal answer details
Close answer details
Question 25
Single choice
You work as a project manager for PassGuide Inc. You want to communicate and solicit feedback from your employees to build future plans. Which of the following will help you to accomplish the above task?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 26
Single choice
You are the project manager of a project to create a network inside of a building. You need to hire an electrician to run network cable throughout the building. Based on your experience, you create an estimate for the work that you'll measure all of the bids against. This is an example of what type of procurement seller selection?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 27
Single choice
Which of the following is a document that covers the work that will be done, how the work will be compensated, and any penalties for noncompliance?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 28
Single choice
You work as a project manager for PassGuide Inc. You have to subdivide project deliverables and project work into smaller, more manageable components. Which of the following processes will you use to perform the above task?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 29
Single choice
Which of the following types of organizations reduces duplication of work because responsibilities are clearly defined on a company-wide basis?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 30
Single choice
Which of the following tools of the Conduct procurements process is used to assign numerical weights to evaluate criteria and then multiply them by the weights of each criteria factor to come up with total scores for each vendor?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 31
Single choice
You work as a project manager for PassGuide Inc. You have to work on an agreement that creates and defines obligations between two or more parties. Which of the following types of agreement will you work on?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 32
Multiple choice
Which of the following are the types of casual/econometric forecasting methods? Each correct answer represents a complete solution. Choose all that apply.
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 33
Single choice
Which of the following refers to the transmission of a message from one person to another in a simple triangle consisting of the context, the sender, the message, and the receiver?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 34
Single choice
You work as a project manager for PassGuide Inc. You have to measure the potential risks on the two dimensions of a graph. Which of the following charts will you use to accomplish the task?
-
A
-
B
Risk probability and impact matrix
-
C
-
D
Reveal answer details
Close answer details
Question 35
Single choice
You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?
-
A
-
B
-
C
-
D
Precedence diagramming method
Reveal answer details
Close answer details
Question 36
Single choice
You are in a project to create a Website. Your project team has met a few times and you're working with them to develop the project's WBS. Jan, a marketing expert, is in disagreement with Larry over how the Website should function. Gary and Gina are in disagreement over who'll take the lead on the design of the software for the Website. Mark, Mary, and Martha are all bickering about the photo management approach for the Website's pictures. What stage of team development is your project team currently in?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 37
Single choice
Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this machine overheat even once it will delay the project's end date. You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down. The temperature of 430 is called what?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 38
Single choice
Jane is the project manager of the GBB project for her company. In the current project a vendor has offered the project a ten percent discount based if they will order 100 units for the project. It is possible that the GBB Project may need the 100 units, but the cost of the units is not a top priority for the project. Jane documents the offer and tells the vendor that they will keep the offer in mind and continue with the project as planned. What risk response has been given in this project?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 39
Single choice
Which of the following elements facilitates people to know large amounts of information as a picture rather than a table of names and numbers?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 40
Single choice
James works as the project manager for a software project. He and his team are on the Direct and Manage Project Execution process. All of the following are inputs of this process except for which one?
-
A
-
B
Approved environmental requests
-
C
Organizational process assets
-
D
Enterprise environmental factors
-
E
Reveal answer details
Close answer details
Question 41
Single choice
Which one of the following best describes a quality metric?
-
A
An operational definition in specific terms what something is and how the quality control processes measures it.
-
B
A value associated with a project process that may be measured in the cost of achieving the process results.
-
C
An operational definition in specific terms what something is and how the quality assurance processes measures it.
-
D
The ability of an entity to satisfy stated and implied needs.
Reveal answer details
Close answer details
Question 42
Single choice
You work as a project manager for PassGuide Inc. You have to subdivide project deliverables and project work into smaller, more manageable components. Which of the following processes will you use to perform the above task?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 43
Single choice
Which of the following process groups involves coordinating with people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan?
-
A
-
B
-
C
-
D
Monitoring and controlling
Reveal answer details
Close answer details
Question 44
Single choice
You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?
-
A
-
B
Implemented corrective action
-
C
-
D
Reveal answer details
Close answer details
Question 45
Single choice
You work as a project manager for PassGuide Inc. You want to enable roll-up of both resource assignments and availability data to a higher level. Which of the following diagrams will help you to accomplish the above task?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 46
Single choice
You are the project manager of TRT project. During execution phase of your project, Rick, a team member, complains that other team members are isolating him and this isolation is bothering him. Which of the following is not a recommended step in order to resolve the issue?
-
A
Apply team building measures to improve the team's effectiveness.
-
B
Get more feed back from Rick.
-
C
Get feedback on Rick from other team members.
-
D
Shift Rick to another project.
Reveal answer details
Close answer details
Question 47
Single choice
Of the following, which best describes the elements in the work breakdown structure (WBS)?
-
A
The elements are the description of the required work.
-
B
-
C
-
D
Elements are part of a weak matrix.
Reveal answer details
Close answer details
Question 48
Single choice
Which of the following processes describes the statement below? "It consists of the processes required to ensure that the project contains all the work required to complete the project effectively."
-
A
Project communications management
-
B
-
C
-
D
Project human resource management
Reveal answer details
Close answer details
Question 49
Single choice
You work as a project manager for PassGuide Inc. You are working on several projects. Your projects vary in size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can compare relative schedule and cost performance of each project. Which of the following components of EVM provide measures of schedule and cost performance that are not affected by the size of the project?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 50
Single choice
Which of the following skills includes vision, gaining consensus for strategic goals, and establishing direction?
-
A
-
B
-
C
Negotiation and Influencing skill
-
D
Reveal answer details
Close answer details
Question 51
Multiple choice
You work as a project manager for PassGuide Inc. You are determining the scope of a project. Which of the following stages should be completed while determining the scope of the project? Each correct answer represents a complete solution. Choose all that apply.
-
A
Identifying the project participants
-
B
Comparing actual project performance against the project management plan
-
C
Determining the information requirements for each participant
-
D
Determining goals and objectives of the project
Reveal answer details
Close answer details
Question 52
Single choice
Which of the following statements describes the critical path?
-
A
It is the shortest path in the project network diagram.
-
B
-
C
It is always one path with the longest duration.
-
D
It shows the project's earliest date for completion.
Reveal answer details
Close answer details
Question 53
Multiple choice
Which of the following are inputs of the Acquire Project Team process? Each correct answer represents a complete solution. Choose all that apply.
-
A
-
B
Organizational process assets
-
C
Enterprise environmental factors
-
D
Reveal answer details
Close answer details
Question 54
Single choice
You are a Project Manager in your organization who is managing a considerably huge budget project to develop new software. Considering the varied nature of your stakeholder group, you would like to put together a plan as to what information the stakeholders need, and how to provide that information. What is the document that you would need, and as part of which process group would you achieve this?
-
A
Communications Management Plan, Execution Process group
-
B
Project Management Plan, Planning Process Group
-
C
Communications Management Plan, Planning Process Group
-
D
Project Management Plan, Initiating Process Group
Reveal answer details
Close answer details
Question 55
Single choice
Your project spans the entire organization. You would like to assess the risk of the project but are worried that some of the managers involved in the project could affect the outcome of any risk identification meeting. Your worry is based on the fact that some employees would not want to publicly identify risk events that could make their supervisors look bad. You would like a method that would allow participants to anonymously identify risk events. What risk identification method could you use?
-
A
-
B
-
C
-
D
Reveal answer details
Close answer details
Question 56
Fill in the blank
Fill in the blank with the appropriate word. ______refers to conveying a message from an individual person to another or to several people, whether verbally or non-verbally
Reveal answer details
Close answer details
Accepted answerAnswer: Communication
Question 57
Multiple choice
Which of the following are outputs of the Control Scope process? Each correct answer represents a complete solution. Choose all that apply.
-
A
Work performance measurement
-
B
Project management plan update
-
C
-
D
Requirement documentation
Reveal answer details
Close answer details
Question 58
Fill in the blank
Fill in the blank with the appropriate term. The______defines the period in which, during the development of the project scope statement, a clear and very thorough project scope statement narrative is documented.
Reveal answer details
Close answer details
Accepted answerAnswer: develop project scope statement period
Question 59
Single choice
Which of the following methods tends to keep the resources levelly loaded, but requires the resources to be flexible in their start times and to quickly switch between tasks and task chains to keep the whole project on schedule?
-
A
-
B
-
C
-
D
Resource leveling heuristics
Reveal answer details
Close answer details
Question 60
Single choice
Micha is the project manager for her project. Micha is now ready to complete the scope verification process so that she can move the project into the project closing process. What is the primary purpose of the scope verification process?
-
A
Review of the project performance
-
B
Acceptance of the project deliverables
-
C
Acceptance of the project team's performance
-
D
Approval that the project has met its objectives
Reveal answer details