  • Question 81:

    A developer has set custom values for the DelayBetweenPagesMS property in the Activity Project Settings. Which activity can be impacted?

    A. Navigate To

    B. Extract Structured Data

    C. Extract PDF Page Range

    D. Attach Browser

  • Question 82:

    A developer uses Workflow Analyzer with the default rules to check if a project follows best practices. In one of the workflows, the Properties of a Click activity is shown in the following exhibit.

    Which Workflow Analyzer rule will trigger a warning for this activity?

    A. Hardcoded Delays

    B. Hardcoded Timeout

    C. Activity Name Defaults

    D. Simulate Click

  • Question 83:

    A developer is building a process which types data into input fields and needs to use the Hardware Events input method. In addition, the developer wants to decrease the speed with which the input string characters are typed into the fields.

    Which property of the Type Into activity should the developer edit?

    A. DelayAfter

    B. WaitForReady

    C. DelayBefore

    D. DelayBetweenKeys

  • Question 84:

    A developer creates a workflow that extracts the date of birth for different account holders in a web application. The following selector represents the selector structure for a 6-digit account number 123456.

    Assume only the account number value changes in the selector and there is a defined list of 6-digit account numbers.

    The developer needs to fine-tune the selector to work only for a pre-selected list of account numbers. What represents an example of a good selector?

    A. Where accountNumber is a 6-digit string variable containing an account number

    B. Where accountNumber is a 6-digit string variable containing an account number

    C. Where accountNumber is a 6-digit string variable containing an account number

    D. Where accountNumber is a 6-digit string variable containing an account number

  • Question 85:

    A developer needs to select a layout for integrating activities into a workflow file. They must select a layout that covers all possible cases and transitions, and accommodate processes that are not easily captured through the use of loops and If statements.

    Based on best practices, which layout is recommended?

    A. Global Exception Handler

    B. Sequence

    C. Flowchart

    D. State Machine

  • Question 86:

    A developer has two collections containing data:

    1) A list of strings called listA that was initialized with 2 items 2) An array of strings called arrayB that was initialized with 2 items How can both collections be combined into a single 4-item collection called results?

    A. Use the Add To Collection activity with arrayB as the parameter

    B. Use the String.Join method with listA and arrayB as parameters

    C. Use a Multiple Assign activity to add each item from arrayB to listA

    D. Use a For Each activity to iterate through listA and add each item to arrayB

  • Question 87:

    In a UiPath project, a developer uses a Click Button activity. A desktop application should be opened as a result of clicking the button. Based on best practice, what should the developer use to ensure:

    (1)

    the button element is clicked and

    (2)

    the application is opened correctly?

    A.

    Modify the Click activity used to open the application by setting the ContinueOnError property to "True"

    B.

    Use an Element Exists activity after the click to ensure that an element exists within the opened application

    C.

    Use the Click activity within the Try Block and in the Catch Block to open the application

    D.

    Use the Click activity in the Action section of a Retry Scope activity with a Condition that an element exists within the opened application

  • Question 88:

    A developer is running a process in UiPath Studio based on Robotic Enterprise (RE) Framework 2021.10. One asset defined in the project does not exist in the Orchestrator folder provided in the Config.xlsx file.

    What is the behavior at runtime?

    A. A warning message stating that the asset is missing is logged and then the process is stopped.

    B. No exception is thrown and neither will a message be logged, the process continues.

    C. The process throws an exception in the Initialization state because the asset is not found, then the process is stopped.

    D. A warning message stating that the asset is missing is logged and then the process continues.

  • Question 89:

    A developer creates a Dispatcher process which extracts information from a Microsoft Excel file and uploads that information into an Orchestrator queue. Based on best practice, what is the recommended way to avoid creating duplicate Queue Items?

    A. Enable the Enforce unique references field of the queue Add a descriptive "Reference" in the Add Queue Item activity

    B. Add a descriptive "Reference" in the Add Queue Item activity Ensure that the "Reference" does not equal the "Reference" of the Queue Item last loaded

    C. Create an Excel file of processed Queue Items Loop through the list to check if the current Queue Item to upload has been uploaded before

    D. Disable the Enforce unique references field of the queue Enable the "Auto Retry" of the queue

  • Question 90:

    What are the differences between partial selectors and full selectors?

    A. Partial selectors are recommended when switching between multiple windows. Full selectors do not include information about the top-level window.

    B. Partial selectors do not include information about the top-level window. Full selectors are recommended to perform multiple actions in the same window.

    C. Partial selectors are recommended to perform multiple actions in the same window. Full selectors include information about the top-level window.

    D. Partial selectors include information about the top-level window. Full selectors are recommended to perform multiple actions in the same window.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only UiPath exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your UIPATH-ARDV1 exam preparations and UiPath certification application, do not hesitate to visit our Vcedump.com to find your solutions here.