What step is used to determine the time period when a risk might occur?
A. Identify - risks
B. Assess - estimate
C. Assess - evaluate
D. Identify context
Which role provides sponsorship to ensure that risk management is embraced within the organization?
A. Senior manager
B. Manager
C. Assurance
D. Risk specialist
Which is NOT an action needed to achieve the goal of the 'assess - evaluate' step?
A. Determine which other risks will occur if a risk occurs
B. Calculate the total risk exposure for the activity
C. Evaluate the effectiveness of risk management across the organization
D. Determine which risks are independent of other risks
What step is used to determine those risks which have the greatest effect on the objectives of a planned activity?
A. Identify
B. Assess
C. Plan
D. Implement
Which is NOT a reason for carrying out an `M_o_R health check?
A. Identify areas for improvement
B. Help gain maximum value from investment in risk management
C. Provide a snapshot of the current status of identified risks
D. Review how well risk management practices have been embedded
Which explains a use of the risk management policy in the identify context' step?
A. Identifies changes to the organization's market
B. Identifies how past events could become sources of risk
C. Describes how corporate governance will affect the risk management process
D. Understand the maximum amount of risk that should be taken
What objectives are associated with decisions on risks to the achievement of long-term goals?
A. Strategic
B. Programme
C. Project
D. Operational
Which does the SWOT analysis technique help to identify about an organization?
A. Long-term trends
B. Stakeholder views
C. Corporate governance requirements
D. Internal strengths
Which technique can be used to clarify potential sources of risks across an activity?
A. Probabilistic risk models
B. Summary risk profiles
C. Risk breakdown structure
D. Decision trees
Which is a purpose of using a risk maturity model?
A. Identify where the application of risk management within an organization can be improved
B. Understand the nature of risks facing an organization and the actions needed to respond
C. Provide independent risk information at key decision points within a programme or project
D. Show to which organizational activities risk management should be applied
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Peoplecert exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PC0-006 exam preparations and Peoplecert certification application, do not hesitate to visit our Vcedump.com to find your solutions here.