  • Question 181:

    Which of the following is NOT an example of a common test metric?

    A. Percentage of work done in test environment creation

    B. Average number of expected defects per requirement

    C. Number of test cases run

    D. Deviation from test milestone dates

  • Question 182:

    What is the difference between system integration testing and acceptance testing?

    A. System integration testing is testing non-functional requirements. Acceptance testing concentrates on the functionality of the system.

    B. System integration testing is executed by the developers. Acceptance testing is done by the customer.

    C. System integration testing verifies that a system interfaces correctly with other systems. Acceptance testing verifies compliance to requirements.

    D. System integration testing verifies compliance to requirements. Acceptance testing verifies correct interaction with other systems existing in the user's environment.

  • Question 183:

    Once a bug is fixed, it should be retested. What is the term used to define this type of testing?

    A. Reliability Testing

    B. Confirmation Testing

    C. Maintainability Testing

    D. Regression Testing

  • Question 184:

    Which of the following is an appropriate reason for maintenance testing?

    A. Bugs found in the field after upgrading the operation system

    B. Bugs found during system testing

    C. Bugs found during unit testing

    D. Bugs found during integration testing

  • Question 185:

    A software company adopts the V-model as their development life cycle. Which of the following contains roles of a tester in this company?

    A. Decide what should be automated, to what degree, and how

    B. Review test plans and set up test environments

    C. Coordinate the test strategy with the project managers

    D. Introduce suitable metrics to measure the testing progress

  • Question 186:

    The following sentences refer to the "Standard for Software Test Documentation" specification (IEEE 829). Which sentence is correct?

    A. The key to high quality test documentation regimes is strict adherence to this standard

    B. Any deviation from this standard should be approves by management, marketing and development

    C. This test plan outline is relevant for military projects. For consumer market projects there is a different specification with fewer items

    D. Most test documentation regimes follow this spec to some degree, with changes done to fit a specific situation or organization

  • Question 187:

    Which of the following is correct?

    A. Intrusive test tools are that do not exhibit the probe-effect

    B. Testing tools can be used by both developers and testers

    C. Use of testing tools is effective only when done as part of a test automation system

    D. Testing tools allow developers do testing. Use of such tools changes the role of the test team

  • Question 188:

    Which of the following errors CANNOT be found with structure-based testing techniques?

    A. Memory is leaking

    B. Features are only partially implemented

    C. Data structures that are used before initialization

    D. Division by zero

  • Question 189:

    Debugging and Testing are key activities in the software development lifecycle.

    Which of the following are 'Debugging' activities?

    a) Identifying, a failure b) Locating the cause of failure c) Fixing the defect d) Checking the fix has resolved the failure

    A. a and d

    B. a and b

    C. b and c

    D. c and d

  • Question 190:

    A new testing tool has been selected for an organisation and a pilot project has successfully completed. The next step is to deploy the tool within the organization. What is a key success factor in tool deployment?

    A. Estimate a cost-benefit ratio based on a firm business case

    B. Determine whether benefits will be achieved at reasonable cost

    C. Provide support for the test team using the tool

    D. Assessment of organisational maturity, strengths and weaknesses

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISTQB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CTFL-FOUNDATION exam preparations and ISTQB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.