  • Question 51:

    Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement?

    A. Test planning and control

    B. Test implementation and execution

    C. Evaluating exit criteria and reporting

    D. Test project closure

  • Question 52:

    Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

    Which TWO mentioned characteristics relate to the phase test plan?

    A. Any deviation from the procedures described in the test

    B. strategy document

    C. The overall estimated costs, timescales and resource

    D. requirements

    E. A detailed schedule of testing activities

    F. The development deliverables to be tested

    G. Which test staff members (names) will be involved and when

    H. Level of requirements coverage achieved

  • Question 53:

    Which of the following product risks would be most effectively addressed just by static testing?

    A. In the delivered application, one of the countries, as specified in the requirements, has not been correctly implemented.

    B. The application takes too long to process a request for additional cover.

    C. The test cases do not cover the key requirements.

    D. The successful bidder may not deliver all the required functionality on time.

  • Question 54:

    Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

    Which THREE mentioned characteristics relate to the master test plan?

    A. Any deviation from the procedures described in the test strategy document

    B. The overall estimated costs, timescales and resource requirements

    C. A detailed schedule of testing activities

    D. The development deliverables to be tested

    E. Which test staff members (names) will be involved and when

    F. Level of requirements coverage achieved

  • Question 55:

    Which one of the following estimation approaches is appropriate at this stage of the project?

    A. Create an estimate based on the function point analysis technique and test point analysis

    B. Create an estimate based on the complexity of the code

    C. Create an estimate based on the credentials of the successful bidder

    D. Create an estimate based on a percentage of the development effort

  • Question 56:

    The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses.

    Which of the following checkpoints would be appropriate?

    A. The bidder's test policy should enforce that incident management fully conforms to IEEE 1044.

    B. The bidder's project strategy shows that the data content of all the test environments conforms to EU standards.

    C. The bidder's test plan shows that the application will be delivered for acceptance in six months time.

    D. The bidder's project test plan depicts a phased implementation with later delivery dates to be confirmed and states that test deliverables will be developed using IEEE 829 as a guide.

  • Question 57:

    Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide?

    A. No priority or severity assigned

    B. Incident numbering is manual rather than automated

    C. No mentioning of reproduceability

    D. No classification on type of incident

  • Question 58:

    The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage?

    A. Percentage of business requirements exercised

    B. Percentage of planned hours worked this week

    C. Percentage of countries that have test scenarios

    D. Percentage of test iterations completed

  • Question 59:

    As a result of the RAD based development approach, the test manager has decided to change the risk mitigation approach.

    Which test technique might be most appropriate to use?

    A. Decision Table Testing

    B. Boundary Value Analysis

    C. Error Guessing

    D. Exploratory Testing

  • Question 60:

    Which of the following is NOT a typical key challenge for testing in a RAD based development approach?

    A. Re-usable test scripts for (automated) regression testing

    B. Project management and control

    C. No complete requirements specification

    D. Time-boxing

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISQI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CTAL-TM exam preparations and ISQI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.