Exam Details

  • Exam Code
    :ATA
  • Exam Name
    :Advanced Test Analyst
  • Certification
    :ISTQB Certifications
  • Vendor
    :ISTQB
  • Total Questions
    :60 Q&As
  • Last Updated
    :May 12, 2024

ISTQB ISTQB Certifications ATA Questions & Answers

  • Question 31:

    For an ATM banking project introduced earlier, "When the user first inserts a valid credit card type, the system considers the user to be in an unauthenticated state. When requesting a cash advance, the user must be in an authenticated state. The user authenticates by entering the proper PIN code. When authenticating the user, the system shall allow the user to enter their PIN code up to three times before failing the authentication and rejecting the card. On the first and second try, the system shall prompt the user to re-enter the PIN code." Suppose you are concerned that, depending on the exact number of invalid PIN codes entered, the system might behave improperly. Which of the following test design techniques is specifically targeted at such failures? [K4] 3 credits

    A. Equivalence Partitioning extended by boundary value analysis

    B. Pairwise Testing with orthogonal arrays

    C. State Transition Testing using 1-switch coverage

    D. Classification Tree Method

  • Question 32:

    While identifying scenario's for the use case "copy A4 ?A4" for a new copier, the following scenario's were identified: Basic scenario: single side to single side Deviations: single side to double side, copy of a set, copy using the automatic document feeder Failures: no paper in paper tray, paper jam, out of staples How many test cases will be needed to achieve minimum coverage? [K3] 2 credits

    A. 1

    B. 4

    C. 5

    D. 7

  • Question 33:

    Which of the following statements is TRUE with respect to when the test analyst should become involved during different lifecycle models? [K2] 1 credit

    A. In a sequential V-model project the test analyst should start test analysis and design concurrently with coding

    B. In Agile projects the test analyst should start test analysis and design concurrently with coding

    C. In a sequential model project the test analyst should start test analysis and design concurrently with software design

    D. In an embedded iterative model the test analyst should expect to be involved in the standard planning and design aspects

  • Question 34:

    A specification states: "If the fossil is Jurassic in origin then it must be catalogued under Mesozoic post

    Triassic and cross referred to politic limestone. If it is a tooth, then it must be catalogued under Dental

    remains. If the fossil is both Jurassic in origin and a tooth it will be catalogued under Mesozoic post

    Triassic and cross referred to politic limestone only. "

    The tester analyses this for decision table testing and finds the following conditions and actions:

    C1: Jurassic C2: tooth A1: Catalogue as Mesozoic post Triassic A2: Cross refer to politic limestone A3:

    Catalogue as

    Dental remains How many test cases will a collapsed decision table have? [K3] 2 credits

    A. 2

    B. 3

    C. 4

    D. 6

  • Question 35:

    A car navigation system needs to be integrated in the overall car software. Interoperability testing is thus considered to be important. Which of the following techniques is most likely be used to support interoperability tests? [K2] 1 credit

    A. Equivalence Partitioning

    B. Statement testing

    C. Vulnerability Scan

    D. Defect Taxonomies

  • Question 36:

    A company offering house insurance policies has several policy options. They depend on the following factors: -Building type: house, semi-detached, apartment building, cottage Material: wood, concrete, brick, mixed Location: city, suburb, countryside, wilderness It has been decided to use the pair wise test technique and apply 2-wise coverage. To design the test case an appropriate orthogonal array needs to be located. Which of the following orthogonal arrays is to be selected for testing the house insurance policies? [K3] 3 credits

    A.

    B.

    C.

    D.

    A. Option A

    B. Option B

    C. Option C

    D. Option D

  • Question 37:

    During the test execution defects are found on non-compliancy to requirements, calculations that produce incorrect results, and improper handling of data or situations. Which of the following test types is most likely being performed? [K2] 1 credit

    A. Usability testing

    B. Interoperability testing

    C. Accuracy testing

    D. Suitability testing

  • Question 38:

    Consider the following description in a defect report "Nasty bug trashed contents of new file that I created by formatting some text in symbol font, wasting my time."

    Which TWO of the following comments would you immediately make based on the defect description above? [K4] 3 credits, 1 out of 2 correct 1 credit

    A. Needs to be neutralized

    B. Steps to reproduce are unclear

    C. No attempt to isolate the defect

    D. More than one defect in one report

    E. Possible duplicate

  • Question 39:

    You are applying pairwise testing and using orthogonal arrays. The following steps are all part of the process to be followed. i) Determine the number of choices for each variable ii) Map the test problem onto the orthogonal array iii) Construct the test cases iv) Identify the variables v) Locate an appropriate orthogonal array

    What is the correct order of the above mentioned process steps? [K3] 2 credits

    A. i, ii, iv, v, iii

    B. iv, ii, v, iii, i

    C. iv, i, iii, v, ii

    D. iv, i, v, ii, iii

  • Question 40:

    You are a test analyst in the banking domain. You have received the following requirement: "The system shall allow cash advances of at least 200 Euros for all supported credit cards. The correct list of credit cards is American Express, Diners, VISA, Mastercard and Eurocard. Which one of the findings described below is true regarding this requirement? [K3] 2 credits

    A. The requirement is ambiguous in terms of supported cards

    B. The paragraph indicates potential performance problems

    C. The paragraph is unclear in terms of advance limits

    D. The paragraph indicates potential usability problems

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISTQB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ATA exam preparations and ISTQB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.