  • Question 161:

    Which of the following tasks are performed within the initiation phase?

    A. Create a WBS

    B. Create a budget

    C. Create a risk register

    D. Create a charter document

  • Question 162:

    Which of the following is the BEST description of a baseline?

    A. A view of the project's status

    B. An assessment of risks for the project

    C. A snapshot of the project at a particular point in time

    D. A calculation of the project's CPI and SPI

  • Question 163:

    Which of the following BEST describes a project risk?

    A. Something that may positively or negatively impact the project

    B. Something that has already affected the project

    C. Something that is outside of the control of the project manager

    D. Something that will negatively impact the project

  • Question 164:

    If the SPI and CPI are both above 1, then the project is:

    A. Behind schedule and under budget.

    B. Behind schedule and over budget.

    C. Ahead of schedule and over budget.

    D. Ahead of schedule and under budget.

  • Question 165:

    Which of the following should be included in a business case? (Select TWO).

    A. A budget estimate with a plus to minus 10%

    B. Benefits to the company

    C. Project Milestones

    D. Cost Benefit Analysis

    E. One proposed option to address the issue

  • Question 166:

    Which of the following areas are addressed in the Project Charter?

    A. Project team members

    B. Work Breakdown Structure (WBS)

    C. Business needs

    D. Communications venue

  • Question 167:

    A project team is reviewing the deliverables and identifies a deliverable no one on the team has experience with. The lack of expertise is identified as a risk. The project manager decides, as a workaround, to contract with a third party. This type of risk response is called:

    A. Transference.

    B. Avoidance.

    C. Monitor and Prepare.

    D. Acceptance.

  • Question 168:

    Which of the following risk strategies can be used to ensure a positive risk is realized?

    A. Accept

    B. Enhance

    C. Share

    D. Exploit

  • Question 169:

    Which of the following risk response planning techniques is a project manager using when they are changing the project plan to remove the risks impact?

    A. Transference

    B. Mitigation

    C. Acceptance

    D. Avoidance

  • Question 170:

    Which of the following plans would MOST likely contain a probability and impact matrix?

    A. Communication

    B. Resource

    C. Risk

    D. Project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.