  • Question 61:

    Scenario:

    Please read this scenario prior to answering the Question You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the Dreadnought Unmanned Aircraft System program.

    Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The decision has been made to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.

    TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing Architecture Development Method (ADM) projects.

    At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving existing processes or systems.

    The architect-re development project has put in place Its Architecture Capability for this project and has started a number of iteration cycles to develop the Architecture. Some tasks to address concerns related to the Business Architecture have been completed. The next immediate task is to address the Information Systems Architectures. The Information Systems Architectures must address stakeholder concerns such as:

    1.

    Which procurement-related business processes are supported by zero, one, or many existing applications?

    2.

    What non-procurement applications will need to be integrated with any new procurement applications?

    3.

    What data will need to be shared?

    Refer to the Scenario

    [Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]

    You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.

    Based on TOGAF 9, which of the following is the best answer?

    A. in the early iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture using a Data Entity/Data Component catalog. In the later Iterations of the Architecture Definition, you would describe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix.

    B. In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.

    C. In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a Data Entity/Business Function matrix and a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.

    D. In the early iterations of Architecture development, you would describe the Baseline Application Architecture with a Technology Portfolio catalog, and describe the Baseline Data Architecture with a Data diagram. In the later iterations of Architecture development, you would describe the Target Application Architecture with a System/Technology matrix, and describe the Target Data Architecture with a Data Dissemination diagram.

  • Question 62:

    Scenario:

    Please read this scenario prior to answering the question

    Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. The company is organized as independent operational divisions.

    The company has a mature Enterprise Architecture practice and uses TOGAF standard for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.

    Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.

    The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment.

    The implementation process is estimated to take four years. Because of the risks posed by the complexity of the current environment, a phased approach is needed to implement the target architectures. The implementation and Migration Plan v0 1, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete.

    Refer to the Scenario

    You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.

    Based on TOGAF standard, which of the following is the best answer?

    A. You would apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. You would confirm the Transition Architecture phases using an Architecture Definition Increments Table to list the projects. You would then document the lessons learned and generate the final plan.

    B. You would assess how the plan impacts the other frameworks in use in the organization. The plan should be coordinated with the business planning, portfolio/project management and operations management frameworks. You would then assign a business value to each project, considering available resources and priorities for the projects. Finally, you would generate the Implementation and Migration Plan.

    C. You would conduct a series of Compliance Assessments to ensure that the implementation team is implementing the architecture according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements should be identified and updated in the Implementation and Migration Plan.

    D. You would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. You would then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be accepted by the Architecture Board as changes to the architecture without review.

  • Question 63:

    Scenario: AGEX Inc.

    Please read this scenario prior to answering the question

    AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.

    Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

    As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.

    The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.

    After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise Architecture program.

    The CIO has endorsed this choice with the full support of top management.

    Refer to the AGEX Inc. Scenario

    You are serving as the Chief Architect.

    As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.

    You have been asked to recommend the best approach for this work.

    Based on TOGAF 9, which of the following is the best answer?

    A. You define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charter. You publish the principles on the corporate intranet to ensure widespread acceptance and compliance. You then schedule regular periodic Compliance Assessments with individual business units to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.

    B. You gather information from credible industry sources in the commodities business. Based on that, you assess current trends and apply that to defining a set of principles that embody best practices. You select architecture principles that do not conflict with each other and that should be stable. You ensure that all the principles are realistic and avoid including principles that are obvious.

    C. You examine the mission statements for AGEX and each of its businesses, together with the corporate value statements. Based on that, you define a set of principles and review with the CIO. When developing the principles you ensure that they actively promote the alignment of IT with the business strategies and initiatives of AGEX. You then seek the endorsement of the CIO and senior management.

    D. You examine the mission statements for AGEX and each of its businesses, together with the corporate value statements. Based on that, you work with the Architecture Review Board to define the principles. When developing the principles you ensure that they actively promote the alignment of IT with the AGEX business strategies. You then run a series of reviews with all the relevant stakeholders, including senior management, ensuring their support.

  • Question 64:

    Worldwide Mobile is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer.

    Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new finding about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. WorldwideMobile actually has better coverage in nearly all markets than Air Light, and good roaming agreement that keep rates low for business travellers. But customer satisfaction has remained low. The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board. The planning for the program has been underway for several months. WorldwideMobile has selected TOGAF 9 as the basis for its Enterprise Architecture. The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Executive Council has stated that the program should define specific initiatives to enable each regional business units to create an implementation of the Customer Service System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer. Refer to WorldwideMobile-2 Scenario You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program.

    The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At present time, the project team is conducting an architecture development project that is focused on the customer self service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device. The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability. You have been asked to recommend the course of action to complete the project. Based on TOGAF 9, which of the following is best answer?

    A. In the remaining architecture definition phases, the project team should map out the capability in the Technology domain. In the Phases E and F, the capability should be broken down into a set of Solution Building Blocks that define the Target Architecture. Where possible, the Solution Building Blocks should be drawn from the Architecture Repository. The completed Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will conduct Compliance Assessments to ensure that the Target Architecture is properly implemented.

    B. In the remaining architecture definition phases, the project team should map out the capability across the Business, Information System and Technology domains. In the Phases E and F, the capability should be broken down into a set of increments that are sequenced into Transition Architectures that will lead to the realization of the Target Architecture. The resulting Solution Building Blocks will then provide the basis for the capability increment solutions. The complete Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conduction Compliance Assessments.

    C. In the remaining architecture definition phases, the project team should map out the capability across the Business, Information System and Technology domains. In the Phases E and F, the capability should be broken down into a set of increments that defines the Target Architecture. The Solution Building Blocks will provide the basis for the capability increment solutions. The complete Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conducting Compliance Assessments.

    D. The remaining architecture definition work should be focused on mapping out the technology and infrastructure capability in the Technology domain. In Phases E and F, the capability should be broken down into a set of Solution Building Blocks that will be implemented to realize the Target Architecture. The Solution Building Blocks will provide the basis for the completed Architecture Definition Document that will be submitted for approval. Upon approval, the implementation team will conduct Compliance Assessments to ensure that the self-service capability is compliant with the overall Enterprise Architecture.

  • Question 65:

    Scenario: Vittronics Ltd.

    Please read this scenario prior to answering the question

    Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.

    This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.

    The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.

    The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.

    The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.

    The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has stated that the changes to the SPICE architecture will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.

    Refer to the Vittronics Ltd Scenario

    You are serving as the Lead Architect for the SPICE project team.

    You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).

    Based en TOGAF 9, which of the following is the best answer?

    A. Create an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps, Solutions and Dependencies Matrix. For each gap, identify a proposed solution and classify it as new development, purchased solution, or based on an existing product. Group similar solutions together to form work packages. Identify dependencies between work packages factoring in the clinical trial schedules. Regroup the packages into a set of Capability Increments scheduled into a series of Transition Architectures and documented in an Architecture Definition Increments Table.

    B. Determine the set of Solution Building Blocks required by identifying which Solution Building Blocks need to be developed and which need to be procured. Eliminate any duplicate building blocks. Group the remaining Solution Building Blocks together to create the work packages using a CRLO matrix. Rank the work packages in terms of cost and select the most cost-effective options for inclusion in a series of Transition Architectures. Schedule the roll out of the work packages to be sequential across the geographic regions.

    C. Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap classify whether the solution is either a new development, purchased solution, or based on an existing product. Group the similar solutions together to define the work packages. Regroup the work packages into a set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials.

    D. Group the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work packages. Using the matrix as a planning tool, regroup the work packages to account for dependencies. Sequence the work packages into the Capability Increments needed to achieve the Target Architecture. Schedule the rollout one region at a time. Document the progression of the enterprise architecture using an Enterprise Architecture State Evolution table.

  • Question 66:

    Scenario: Rollins Manufacturing

    Please read this scenario prior to answering the question

    Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.

    Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third- party contractor could provide those staff.

    The Rollins Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.

    The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.

    Refer to the Rollins Manufacturing Scenario

    You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture project team.

    As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they know a solution that will work. During the meeting, a number of alternative recommendations for how to proceed are put forward by members of the team. You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.

    Based on TOGAF 9, which of the following is the best answer?

    A. The team should hold a series of interviews at each of the manufacturing plants using the business scenario technique. This will then enable them to identify and document the characteristics of the architecture from the business requirements.

    B. The team should exercise due diligence and carefully research vendor literature and conduct a series of briefings with vendors that are on the current approved supplier list. Based on the findings from the research, the team should define a preliminary target Architecture Vision. The team should then use that model to build consensus among the key stakeholders.

    C. The team should create Baseline and Target Architectures for each of the manufacturing plants. A gap analysis between the architectures will then validate the approach, and determine the Transition Architecture needed to achieve the target state.

    D. The team should conduct a pilot project that will enable vendors on the short list to demonstrate potential solutions that will access the concerns of the stakeholders. Based on the findings of that pilot project, a complete set of requirements can be developed that will arrive the evolution of the architecture.

  • Question 67:

    Scenario: Zephyr Enterprises

    Please read this scenario prior to answering the question

    Zephyr Enterprises specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. Zephyr has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Ontario. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturers design specifications.

    Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. Zephyr has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.

    Zephyr has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.

    Zephyr has used TOGAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have recently updated to TOGAF 9 and have adapted the Zephyr Enterprise Architecture to closely follow the TOGAF 9 framework. All of Zephyrs IT architects have been trained and certified on TOGAF 9.Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance

    tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for

    immediate implementation at each plant.

    An Architecture Contract was developed that detailed the work needed to implement and deploy the new

    Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern

    that a uniform process be employed at each site to ensure consistency.

    Refer to the Zephyr Enterprises Scenario:

    You have been assigned by the Lead Architect for the Automated Test System controller project to

    conduct Compliance Assessments at each manufacturing plant.

    During the course of the assessment at the Omaha plant, you discover that the Distributed Data

    Acquisition System they have purchased uses a proprietary Remote Procedure Call (RPC) that utilizes

    kernel mode threads instead of the user mode threads that are specified in the Architecture Definition

    Document. In all other respects, the system meets the requirements stated in the Architecture Definition

    Document and seems to perform correctly.

    You have been asked to describe the compliance of this system for the final report.

    Based on TOGAF 9, which of the following is the best answer?

    A. You observe that all of the features in the Architecture Definition Document have been implemented in accordance with the specification, except for the RPC mechanism. Your recommendation is that the system be described as conformant.

    B. You observe that the system has many features in common with the Architecture Definition Document, and those features have been implemented in accordance with the specification. However, you note that the RPC mechanism has been implemented using features that are not covered by the specification. Your recommendation is that the system be described as consistent.

    C. You observe that the implementation of the RPC mechanism has no features in common with the Architecture Definition Document, therefore the question of its conformance should not be considered. Your recommendation is that the system be described as consistent.

    D. You observe that the system meets most of the requirements stated in the Architecture Definition Document and appears to work correctly. However, you note that the RPC mechanism has not been implemented according to the specification. Your recommendation is that the system be described as non-conformant.

  • Question 68:

    Scenario: St. Croix Consulting

    Please read this scenario prior to answering the question

    St. Croix Consulting started as an accounting and financial services company. It has expanded over the years and is now a leading North American IT and Business Services provider.

    With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings. Senior partners must become team players, working to support the broader needs of the company and its shareholders.

    The Enterprise Architecture team has been working to create St. Croixs Enterprise Architecture framework to address these issues. The team has defined a preliminary framework and held workshops with key stakeholders to define a set of principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period.

    An Architecture Review Board has been formed comprised of IT staff executives and executives from the major practice areas.

    The Enterprise Architecture framework is based on TOGAF 9.

    The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of the Enterprise Architecture program.

    Refer to the St Croix Consulting Scenario:

    You have been assigned to the role of Chief Enterprise Architect.

    As the EA team prepares to formulate an Implementation plan, they have been asked by the CIO to assess the risks associated with the proposed architecture. He has received concerns from senior management that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.

    You have been asked to recommend an approach to satisfy these concerns.

    Based on TOGAF 9, which of the following is the best answer?

    A. An interoperability analysis should be applied to evaluate any potential issues across the Solution Architecture. Once all of the concerns have been resolved, the EA team should finalize the Architecture Implementation Roadmap and the Migration Plan.

    B. The EA team should gather information about potential solutions from the appropriate sources. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.

    C. Prior to preparing the Implementation plan, the EA team should create a consolidated gap analysis to understand the transformations that are required to achieve the proposed Target Architecture. The EA team should gather information about potential solutions from the appropriate sources. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures. An interoperability analysis should be applied to evaluate any potential issues across the Solution Architecture.

    D. Prior to preparing the Implementation plan, there are several techniques that should be applied to assess the risks and value of the proposed transformation. In particular, the EA team should pay attention to the Business Transformation Readiness Assessment and the Business Value Assessment.

  • Question 69:

    Scenario: Armstrong Defense Industries Please read this scenario prior to answering the question

    Armstrong Defense Industries is the prime contractor for the Dreadnought Unmanned Aircraft System program.

    Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. Armstrong Defense is moving aggressively to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.

    To achieve this goal, Armstrong Defense needs to define Baseline and Target Architectures. These architectures must address key stakeholders concerns such as:

    1.

    What groups of people should be involved in procurement-related business processes?

    2.

    What current applications do those groups use?

    3.

    Which procurement-related business processes are supported by zero, one, or many existing applications?

    4.

    What are the overall lifetimes of the Request for Proposal and Purchase Order business objects?

    5.

    What non-procurement applications will need to be integrated with any new procurement applications?

    6.

    What data will need to be shared?

    At present, there are no particularly useful architectural assets related to this initiative. All assets need to be acquired and customized or created from scratch. The company prefers to implement existing package applications from systems vendors with little customization.

    The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle.

    Armstrong Defense is using TOGAF for its internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture Development Method (ADM) projects.

    Refer to the Armstrong Defense Industries Scenario

    You are serving as the Lead Architect.

    You have been asked to identify the most appropriate architecture viewpoints for this situation.

    Based on TOGAF 9, which of the following is the best answer?

    A. In the early iterations of the Architecture Definition:

    Describe the Baseline Business Architecture with a Baseline Business Process catalog

    Describe the Baseline Application Architecture with a Technology Portfolio catalog

    Describe the Baseline Data Architecture with a Data diagram

    In the later iterations of the Architecture Definition:

    Describe the Target Business Architecture with an Actor/Process/Data catalog

    Describe the Target Application Architecture with a System/Technology matrix

    Describe the Target Data Architecture with a Data Dissemination diagram

    B. In the early iterations of the Architecture Definition:

    Describe the Target Business Architecture with a Business Service/Function catalog and a Business

    Interaction matrix

    Describe the key business objects with Product Lifecycle diagrams

    Describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix

    Describe the Target Data Architecture with a Data Entity/Business Function matrix and a System/ Data matrix

    In the later iterations of the Architecture Definition:

    Describe the Baseline Business Architecture with a Business Service/Function catalog and a

    Business Interaction matrix

    Describe the Baseline Application Architecture with a System/Organization matrix and a System/ Function matrix

    Describe the Baseline Data Architecture with a Data Entity/Data Component catalog

    C. In the early iterations of the Architecture Definition:

    Describe the Target Business Architecture with a Business Service/Function catalog and an

    Organization/Actor catalog

    Describe the key business objects with Data Lifecycle diagrams

    Describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix

    Describe the Target Data Architecture with a System/Data matrix

    In the later iterations of the Architecture Definition:

    Describe the Baseline Business Architecture with a Business Service/Function catalog and a

    Business Interaction matrix

    Describe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrix

    Describe the Baseline Data Architecture with a Data Entity/Data Component catalog

    D. In the early iterations of the Architecture Definition:

    Describe the Baseline Business Architecture with an Organization/Actor catalog

    Describe the Baseline Application Architecture with a System/Function matrix

    Describe the Baseline Data Architecture using a Data Entity/Data Component catalog

    In the later iterations of the Architecture Definition:

    Describe the Target Business Architecture with en Organization/Actor catalog

    Describe the Target Application Architecture using Application Communication diagrams end an Application Interaction matrix

    Describe the Target Data Architecture with a System/Data matrix

  • Question 70:

    Scenario: Florian Flowers BV

    Please read this scenario prior to answering the question

    Florian Flowers BV is an international agricultural company exporting flowers and seeds worldwide. Florian

    is headquartered in Rotterdam in the Netherlands, and has sales and distribution centers in over 60

    countries worldwide. Several of these centers include administrative, manufacturing, and research

    facilities.

    To achieve full integration of their research capabilities with their development centers located in various

    climate zones, Florian wants to develop strong self-directed teams in each location. Florian also wants to

    define new business models that are profitable while reducing their impact on the environment. Florian

    management is deeply committed to ensuring that the company is a world leader in socially responsible

    seed development with a business strategy that focuses on profitability through environmentally friendly

    operating processes.

    Florians international operations are subject to various legal and regulatory requirements. In areas such as

    genetically modified seeds, governmental controls are strictly enforced and compliance is critical. Recently

    a competitor was heavily fined for violating the regulations in a country where it was developing pest-

    resistant seeds.

    The Governing Board is concerned, and as a result has approved the expenditure of resources to

    establish an Enterprise Architecture program. They have requested to be informed about the status of

    projects that could impact regulatory compliance. They also want to enable the corporate legal staff and

    auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given

    location. In addition, the research organization should be able to see that the architecture is appropriate for

    its needs.

    TOGAF 9 has been mandated as the guiding framework for the development and evolution of the

    Enterprise Architecture practice.

    Refer to the Florian Flowers BV Scenario

    Florian management has engaged you as the Lead Consultant to assess the current situation.

    You have been asked to recommend an approach that would enable the development of an architecture

    that addresses the needs of all these parties.

    Based on TOGAF 9, which of the following is the best answer?

    A. Depending on the nature of the architecture, a set of models should be created that can be used to ensure that the system will be compliant with the local regulations. Stakeholders should be able to view the models to see that their concerns have been properly addressed.

    B. Each architecture activity should be developed using a consistent modeling approach that is uniform across all architecture projects. Each architecture should be defined based on this fixed set of models so that all concerned parties can examine the models to ensure that their issues and concerns have been accessed.

    C. For those groups that have sufficient power and level of interest, a special report should be created that summarizes the key features of the architecture with respect to the particular location. Each of these reports should reflect the stakeholders' requirements.

    D. It would be beneficial to develop a stakeholder map that allows the architects to define groups of stakeholders that share common concerns. A set of views should be defined that addresses the concerns each group. Architecture models can then be created for each view to address the stakeholders' concerns.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only The Open Group exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your OG0-092 exam preparations and The Open Group certification application, do not hesitate to visit our Vcedump.com to find your solutions here.