Which one of the following best describes the purpose of a Change Request?
A. To act as a deliverable container for artifacts created during a project
B. To ensure that the results of a Compliance Assessment are distributed to the Architecture Board
C. To request a dispensation or to kick-start a further cycle of architecture work
D. The ensure that information is communicated to the right stakeholders at the right time
E. To review project progress and ensure the implementation is inline with the objectives
What level of risk is the risk categorization prior to determining and implementing mitigating actions?
A. Marginal
B. Residual
C. Low
D. Initial
E. Critical
Complete the sentence. The major information areas managed by a governance repository should include __________________.
A. Common Systems Solutions, Organization-Specific Solutions and Industry Solutions
B. Catalogs, Matrices and Diagrams
C. Artifacts, Best Practices and Standards
D. Audit Information, Process Status and Reference Data
E. Capability, Segment, and Transition Architectures
In which ADM Phase is the focus the creation of an Implementation and Migration Plan in co-operation with the portfolio and project managers?
A. Phase A
B. Phase F
C. Phase D
D. Phase G
E. Phase E
What are considered as generic Building Blocks in the Solutions Continuum?
A. Common Systems Solutions
B. Strategic Solutions
C. Industry Solutions
D. Organization-Specific Solutions
E. Foundation Solutions
What version number does the TOGAF ADM use to indicate that a high-level outline of the architecture is in place?
A. Version 0.5
B. Version 0.7
C. Version 1.0
D. Version 0.1
E. Version 0.9
What is an objective of ADM Phase G, Implementation Governance?
A. To ensure that implementation projects conform with the Target Architecture
B. To ensure that the enterprise's Architecture Capability meets current requirements
C. To assess the performance of the architecture and make recommendations for change
D. To establish the value realization process
E. To prioritise the projects through risk validation
In which part of the ADM cycle do the earliest building block definitions start as abstract entities?
A. Phases E and F
B. Preliminary Phase
C. Phase B, C, and D
D. Phase G and H
E. Phase A
What is an objective of the ADM Preliminary Phase?
A. To create the initial version of the Architecture Roadmap
B. To develop a vision of the business value to be delivered by the proposed enterprise architecture
C. To select and implement tools to support the Architecture Capability
D. To obtain approval for the Statement of Architecture Work
E. To document the baseline architecture
What are the four architecture domains that the TOGAF standard deals with?
A. Capability, Segment, Enterprise, Federated
B. Business, Data, Application, Technology
C. Application, Data, Information, Knowledge
D. Process, Organization, Strategic, Requirements
E. Baseline, Candidate, Transition, Target
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only The Open Group exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your OG0-091 exam preparations and The Open Group certification application, do not hesitate to visit our Vcedump.com to find your solutions here.