Which of the following may require a modification to the project scope baseline?
A. An approved project change request
B. A team member removed from the project
C. A task that is falling behind schedule
D. An identified product quality issue
Which of the following is the MOST common relationship used, when constructing a project schedule network diagram?
A. Start-to-Finish
B. Finish-to-Start
C. Start-to-Start
D. Finish-to-Finish
Which of the following sequences represents the correct order for implementing a change request?
A. Change is requested, change impact analyzed, change request submitted to board, change request approved, change implemented.
B. Change is requested, change implemented, change impact analyzed, change request submitted to board, change request approved.
C. Change is requested, change request submitted to board, change impact analyzed, change request approved, change implemented.
D. Change is requested, change request submitted to board, change request approved, change implemented, change impact analyzed.
Although there is a difference of opinion among several team members, the project managers authority is used to keep the project moving forward. Which of the following conflict resolution techniques is being used by the project manager?
A. Forcing
B. Avoiding
C. Negotiating
D. Confronting
Which of the following conflict resolution techniques is described as having one of the conflicting parties not deal with the problem?
A. Negotiating
B. Compromise
C. Smoothing
D. Avoiding
Refer to the attached Exhibit.
Which of the following dependencies is demonstrated between task 1 and task 2 in the following diagram?
A. Start-to-Start
B. Start-to-Finish
C. Finish-to-Finish
D. Finish-to-Start
The greatest amount of conflict occurs in which of the following team development stages?
A. Storming
B. Performing
C. Norming
D. Forming
Two employees do not want to work with each other. The project manager tells the employees to perform the tasks or find other employment. Which of the following conflict resolution styles is being used?
A. Forcing
B. Withdrawing
C. Compromising
D. Accepting
Two employees will not work on the same project together. The project manager tells the employees to talk to their supervisors because the supervisors recommended they work together. This is an example of which of the following conflict resolution styles?
A. Withdrawing
B. Forcing
C. Accepting
D. Compromising
A project manager has noted that a vendor is providing a poor quality product. The vendor states that its products meet the quality standards outlined in the current contract. Which of the following documents outline the contractual requirements?
A. The statement of work (SOW)
B. The milestone schedule
C. The request for proposal (RFP)
D. The work breakdown structure (WBS)
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.