  • Question 81:

    Which ordering of the list below gives increasing levels of test independence?

    a) Tests designed by a fellow-member of the design team. b) Tests designed by a different group within the organisation. c) Tests designed by the code author.

    d) Tests designed by different organisation.

    A. c, a, b, d

    B. d, b, a, c

    C. c, a, d, b

    D. a, c, d, b

  • Question 82:

    Which of the following are the typical defects found by static analysis tools?

    a) Variables that are never used.

    b) Security vulnerabilities.

    c) Poor performance.

    d) Unreachable code.

    e) Business processes not followed.

    A. b, c and d are true; a and e are false

    B. a is true; b, c, d and e are false

    C. c, d and e are true; a and b are false

    D. a, b and d are true; c and e are false

  • Question 83:

    Which ADDITIONAL test level could be introduced into a standard V-model after system testing?

    A. System Integration Testing

    B. Acceptance Testing

    C. Regression Testing

    D. Component Integration Testing

  • Question 84:

    The above table shows 6 test procedures (P to U) that must now be entered into a test execution schedule. Business severity is regarded as the most important element in determining the sequence of the test procedures, but other dependencies must also be taken into consideration. Regression testing can only be run once all other tests have completed.

    Which of the following represents the MOST effective sequence for the test execution schedule (where the first entry in the sequence is the first procedure to be run, the second entry is the second to be run and so on)?

    A. Q, P, S, R, U, T.

    B. R, S, U, P, Q, T.

    C. R, P, S, U, T, Q.

    D. P, Q, R, S, U, T

  • Question 85:

    Which of the following statements is true?

    A. Testing cannot prove that software is incorrect.

    B. Testing can prove that software is either correct or incorrect.

    C. Testing cannot prove that software is correct.

    D. Testing can prove that software is correct.

  • Question 86:

    What is the USUAL sequence for performing the following activities during the Fundamental Test Process?

    a) Analyse the test basis documents.

    b) Define the expected results.

    c) Create the test execution schedule.

    d) Establish the traceability of the test conditions

    A. d, a, c, b

    B. a, d, b, c

    C. a, b, c, d

    D. a, b, d, c

  • Question 87:

    From a Testing perspective, what are the MAIN purposes of Configuration Management?

    a) Identifying the version of software under test.

    b) Controlling the version of testware items.

    c) Developing new testware items.

    d) Tracking changes to testware items.

    e) Analysing the need for new testware items.

    A. b, d and e

    B. b, c and d

    C. a, b and d

    D. a, c and e

  • Question 88:

    Which of the following BEST describes a data-driven approach to the use of test execution tools?

    A. Monitoring response times when the system contains a specified amount of data

    B. Manipulation of databases and files to create test data

    C. Using a generic script that reads test input data from a file

    D. Recording test scripts and playing them back

  • Question 89:

    During which activity of the Fundamental Test Process test process do you review the test basis?

    A. Evaluating exit criteria and reporting.

    B. Test implementation and execution

    C. Test analysis and design

    D. Test planning and control

  • Question 90:

    How is the scope of maintenance testing assessed?

    A. Scope is related to the risk, size of the changes and size of the system under test

    B. Scope is defined by the size and type of system being changed

    C. Scope is defined by the size and type of system being changed

    D. Scope is related to the number of system users affected by the change.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISEB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ISEB-SWT2 exam preparations and ISEB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.