IASSC Lean Six Sigma Green Belt ICGB Questions & Answers

  • Question 21:

    Training cost $6,500 and a project required an initial investment of $47,500. If the project yields monthly savings of $3,500 beginning after 4 months, what is the payback period in months, before money costs and taxes?

    A. 9.7

    B. 15.4

    C. 19.4

    D. 23.7

  • Question 22:

    Which of these statements describe an undesirable situation when implementing SPC? (Note: There are 2 correct answers).

    A. The lower Control Limit for the R chart is equal to zero

    B. The Control Limits are wider than the customer specification limits

    C. A process is in Statistical Control before implementation of SPC

    D. Attempt to use SPC for tracking transaction times at a warehouse

    E. Indication of the specification limits on the Control Chart

  • Question 23:

    SPC charts typically have the most recent data point on the right hand side.

    A. True

    B. False

  • Question 24:

    Significant variation in process performance is a consequence of several causes that can be classified using terminologies shown here. (Note: There are 2 correct answers).

    A. Common

    B. Random

    C. Uneducated

    D. Special

    E. Vital

  • Question 25:

    The reason(s) for not marking the customer Specification Limits (SL) on a Control Chart is which of these? (Note: There are 4 correct answers).

    A. Process control teams should not control a process based on SLs

    B. Displaying the SLs on a Control Chart sends a wrong signal toward process control

    C. Marking the SLs on a Control Chart is against the principle of charting

    D. By marking the SLs, one can confuse the operator as to what limits are critical

    E. By using mere Control Limits the process only needs to be in Statistical Control

  • Question 26:

    The practice of utilizing Poka-Yoke is also known as ________________.

    A. Thorough integration

    B. Mistake proofing

    C. On site inspection

    D. Lean controls

  • Question 27:

    Examples of Mistake Proofing for a laptop computer include which of these? (Note: There are 2 correct answers).

    A. USB connection for a mouse

    B. Open/Close button for CD Drive

    C. Battery alignment pins

    D. On/Off switch for computer

  • Question 28:

    Standardized work instructions apply to which resource in the process of interest?

    A. People

    B. Machines

    C. Supervision

    D. Engineering

  • Question 29:

    As part of a Visual Factory plan Kanban cards are created and utilized to identify areas in need of cleaning and organization.

    A. True

    B. False

  • Question 30:

    Examples of a Visual Factory include which of these? (Note: There are 2 correct answers).

    A. White outlines on floor for proper inventory placement

    B. Documented procedures with a numerical outline

    C. Bad/Good indications of gauge readings with red and green outlines D. Implementing a defect inspection device

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IASSC exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ICGB exam preparations and IASSC certification application, do not hesitate to visit our Vcedump.com to find your solutions here.