Which of the following statements is false?
A. Technical requirements do not contribute to the functional size
B. CPM is transformed into an ISO standard for size with inclusion of GSC
C. Functional size can be estimated in the proposal phase
D. Prior to FP counting, we need to determine the purpose of the count
When counting an EI, which of the following statements is true of the term maintain?
A. It is the ability to create or modify an elementary process
B. It is the ability to create data in another application
C. It is the ability to add, change or delete data through the elementary process
D. None of the above
An External Input is an elementary process that:
A. Processes data or control information sent from outside the boundary
B. Has the primary intent to maintain one or more ILFs
C. has the primary intent to alter the behavior of the system
D. All of the above
Which of the following statements is (are) true regarding the definition of maintain? Maintain is defined as:
A. Ability to add, change or delete transactions through an elementary process
B. Ability to add, change or delete data through an elementary process
C. Ability to add, change or delete data through a functional user requirement
D. None of the above
Which is the first step of the Measurement process?
A. Gather the available documentation
B. Determine the counting scope and application boundary
C. Measure data functions
D. Measure transactional functions
Which type of functional size (FS) measures the functionality added, changed, or deleted at the completion of an enhancement project?
A. Application FS
B. Baseline FS
C. Enhancement project FS
D. Development project FS
An application's functional size is also referred to as the installed functional size. When is the application functional size updated?
A. Never, the application functional size is the baseline or installed functional size
B. Once a year if there were enhancement projects that altered the application functions
C. Every time completion of an enhancement project alters the application's functions
D. The application is re-counted once a year regardless of the number of enhancement projects
The boundary for the function point count:
A. encloses the physical data maintained by the application
B. is based on the user view, not on technical considerations
C. is the conceptual interface between the internal user world and external application world
D. is dependent on implementation and/or technical considerations
What indicates the conceptual interface between the software under study and its users?
A. The boundary membrane
B. The application interface
C. The boundary interface
D. The boundary
Conversion functionality is defined as:
A. transactional or data functions provided to convert data and/or provide other user specified conversion requirements
B. conversion functionality required by the developer
C. a measure of the conversion functionality delivered to the user when the project is complete
D. a measure of the data that is converted for the user when the project is complete
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IFPUG exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your I40-420 exam preparations and IFPUG certification application, do not hesitate to visit our Vcedump.com to find your solutions here.