Dassault Systemes ENOVIA ENOV612-PRG Questions & Answers

  • Question 31:

    What does the red square in the following image, indicate?

    A. The task is not complete and the current date is afer the task estmated fnish date

    B. The task is not complete and there are less than 5 days before the project's estmated fnish date

    C. The task is complete

    D. The task has not started

  • Question 32:

    When defning the task duraton, you can do it in...

    A. Days

    B. Hours

    C. Fractons

    D. All of these are possable

  • Question 33:

    For a project that has 2 tasks and no dependencies that take the same number of days to fnish, the critcal path is:

    A. the frst task to fnish

    B. the frst task to start

    C. none of the tasks

    D. both are critcal

  • Question 34:

    In a project with 2 tasks, and no dependencies, the critcal path is identfed in Red and is the:

    A. frst task

    B. one with the longest tme to fnish

    C. second task

    D. one with the shortest tme to fnish

  • Question 35:

    If no dependencies are added to the tasks,

    A. the start and end dates are all the same

    B. the start dates are all the same and the end dates are automatcally adjusted according to the duraton entered

    C. the start dates are the same with the end date the project end date

    D. the start dates of the tasks are automatcally adjusted according to the duraton entered

  • Question 36:

    In additon to tasks dependencies, how can you specify a delay between tasks?

    A. with Slack Time in days or hours

    B. with Start Delay tme in days or hours

    C. with Start-to-Start tme in hours

    D. None of these

  • Question 37:

    Int the following image, what does the dependency (FS) specify?

    A. Import the points WBS task must fnish before the Filter the points task can start

    B. Import the points WBS task must start before the Filter the points task can fnish

    C. Import the points WBS task must fnish before the Filter the points task can fnish

    D. Import the points WBS task must start before the Filter the points task can start

  • Question 38:

    Which dependency code do you assign if the current task CANNOT fnish untl another task starts?

    A. Finish-To-Finish

    B. Finish-To-Start

    C. Start-To-Finish

    D. Start-To-Start

  • Question 39:

    Your project has a task called Create Student Guide (Task #3) which CANNOT start untl Review Course Outline (Task #2) fnishes. What is the correct dependency code?

    A. 2:FS on Create Student Guide

    B. 2:SF on Create Student Guide

    C. 3:FS on Review Course Outline

    D. 3:FF on Review Course Outline

  • Question 40:

    Which dependency code do you assign if the selected task CANNOT start untl the current task starts?

    A. Finish-To-Finish

    B. Finish-To-Start

    C. Start-To-Finish

    D. Start-To-Start

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Dassault Systemes exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ENOV612-PRG exam preparations and Dassault Systemes certification application, do not hesitate to visit our Vcedump.com to find your solutions here.