What makes network-critical physical infrastructure (NCPI) management different from traditional building management systems?
A. Availability of safety resources
B. Safety of the people in the building
C. Availability of computing resources
D. Comfort of the people in the building
What is the proper sequence for developing a management strategy?
A. Set and measure Availability targetsImplement an Incident Management strategy
B. Put Change Management processes in placeSet and measure Availablity targets
C. Implement an Incident Management strategyMonitor and plan for long term changes in Capability
D. Monitor and plan for long term changes in CapacityPut Change Managment processes in place
When developing a management strategy, how long do organizations typically focus on fully implementing each management process before moving on to the next?
A. One to three months
B. Three to six months
C. Six to nine months
D. Nine to twelve months
Which management challenge can provide advance warning for failure?
A. Change management
B. Incident management
C. Capacity management
D. Availability management
Which two elements should be included in an effective NCPI management system? (Choose two.)
A. Defining owner roles
B. Monitoring of network traffic
C. Communicating data storage thresholds
D. Identifying the impact of individual component problems
Which is an example of an NCPI management system data point?
A. Monitoring of network traffic
B. Mislabeling of kirk-key interlock
C. Advanced warning of UPS battery deficiency
D. Reading of boiler room steam pressure levels
Which NCPI management technique specifically addresses the challenge of maintaining spare equipment at compatible firmware revision levels to avoid downtime?
A. Change management
B. Capacity management
C. Reliability management
D. Availability management
Which management technique provides the ability to set and assign owner roles?
A. Incident management
B. Availability management
C. Accountability management
D. Owner resolution management
A planning challenge for data center managers is to find an NCPI solution that allows incremental purchases of necessary resources on short time frames. Which type of NCPI management is concerned with this challenge?
A. Change management
B. Incident management
C. Capacity management
D. Availability management
Planned downtime is necessary for many data centers. management tools that ignore planned downtime can have which consequence?
A. Spurious alerts leading to incorrect actions by personnel
B. Insufficient runtime specifications for blade server deployments
C. Downtime that can result from individual components failing
D. Reduction in the training and knowledge that is necessary to maintain the NCPI system
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APC exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your DU0-001 exam preparations and APC certification application, do not hesitate to visit our Vcedump.com to find your solutions here.