  • Question 51:

    What is the MOST important reason why test conditions should be understandable by stakeholders?

    A. They should be able to review the test conditions and provide feedback to the test analyst

    B. They should be able to use them as a basis for designing test cases

    C. They should be able to use them to establish traceability to requirements

    D. Test documentation should always be understandable by all stakeholders

  • Question 52:

    Working together with the test manager during test planning, which of the following activities is NOT expected to be performed by the test analyst?

    A. Review the test estimates of the test manager

    B. Review the test plan for non-functional testing

    C. Organize adequate test resources

    D. Being involved in risk management sessions

  • Question 53:

    A specification states: "If the fossil is Jurassic in origin then it must be catalogued under Mesozoic post Triassic and cross referred to politic limestone.

    If it is a tooth, then it must be catalogued under Dental remains. If the fossil is both Jurassic in origin and a tooth it will be catalogued under Mesozoic post Triassic and cross referred

    to politic limestone only. "

    The tester analyses this for decision table testing and finds the following conditions and actions:

    C1: Jurassic C2: tooth A1: Catalogue as Mesozoic post Triassic A2: Cross refer to politic limestone A3: Catalogue as Dental remains How many test cases will a collapsed decision table have?

    A. 2

    B. 3

    C. 4

    D. 6

  • Question 54:

    While identifying scenario's for the use case "copy A4 ?A4" for a new copier, the following scenario's were identified: Basic scenario: single side to single side

    Deviations: single side to double side, copy of a set, copy using the automatic document feeder

    Failures: no paper in paper tray, paper jam, out of staples

    During interviews with both development and end-users it has been established that the failure scenario's can occur during the basic scenario and during each of the deviations.

    How many test cases will be needed to achieve full coverage both for valid and invalid situations?

    A. 10

    B. 12

    C. 16

    D. 20

  • Question 55:

    A temperature unit holds the temperature between 10 degrees Celcius and ?0 degrees Celcius. If the temperature drops below ?0 or rises above 10 then an alarm rings. Boundary Value Analysis tests are drawn up using the approach of two test cases per boundary. The temperatures to be tested are:

    A. 11, 10, -11, -10

    B. 11, 10, 9, -11, -10, -9

    C. 11, 9, -9, -11

    D. 10, 9, -9, -10

  • Question 56:

    Which of the following is a type of testing that someone in the role of a test analyst, working with the test manager, should typically consider and plan for?

    A. Security testing

    B. Reliability testing

    C. Accessibility testing

    D. Performance testing

  • Question 57:

    A car navigation system needs to be integrated in the overall car software. Interoperability testing is thus considered to be important. Which of the following techniques is most likely be used to support interoperability tests?

    A. Equivalence Partitioning

    B. Statement testing

    C. Vulnerability Scan

    D. Defect Taxonomies

  • Question 58:

    Which of the following criteria on test progress would enable the business to determine a likely `go live' date?

    (i)

    Number of tests planned versus number of tests executed

    (ii)

    Number of high priority defects outstanding

    (iii) The test team's timesheets in order to show how much effort has been devoted to testing

    (iv)

    Number of tests passed and number failed

    (v)

    Number of defects found in each development area

    (vi)

    The rate at which defects are being found

    A.

    (ii), (iii), (iv)

    B.

    (i), (iii), (v)

    C.

    (i), (ii), (vi)

    D.

    (iv), (v), (vi)

  • Question 59:

    How many invalid test cases can be identified from the "Route Calculation" state table provided? You may assume all actions are different and independent.

    A. 6

    B. 8

    C. 102

    D. 12

  • Question 60:

    Ken, an entrepreneur in Leeds finds the quality of the tea locally available so low, that he decides to research superior teas around the world. He decides to market, sell and distribute these superior teas via the web. His market strategy is to offer superior products on a well-designed website with graphics that are fast to load, has high availability, superior usability and fast response times.

    The website will offer the following:

    - An innovative interactive catalogue of teas, which not only enables customers to buy the product, but also enables them to provide feedback by rating the teas (which will influence his stock purchasing levels)

    -

    Provide the customer with the ability to use secure credit card transactions

    -

    Provide the customer to give general feedback

    Ken selects an iterative model for the development of the prototypes. The team consists of three developers that are experienced in web development. Ken, although he doesn't have technical skillset, is concerned with quality. He doesn't

    believe a lot of documentation is necessary and he wants the website to be completed quickly.

    The test basis contains the following:

    -Story boards that show the information flow and page links through the site

    -HTML pages developed to date.

    -

    A statement of non-functional requirements.

    With the strategy taking shape, Ken asks your advice on the specific testing techniques that should be used to complete the required testing, bearing in mind the nature of the application and the nature of Ken's overall objectives.

    Which TWO of the following items may more frequently need to be explained in greater detail for non-functional defect reports than for a functional defect report?

    A.

    Expected results

    B.

    Steps to reproduce the defect

    C.

    Test data used to identify the fault

    D.

    Level of load on the system at the time of failure

    E.

    Actual results

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISQI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CTAL-TA_SYLL2012_UK exam preparations and ISQI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.