A _____________________ is created during the first half of the Sprint planning meeting and a _________________ is created during the second half of the Sprint planning meeting?
A. Sprint Backlog, collection of tasks
B. Product Backlog, collection of tasks
C. Sprint Goal, Sprint Backlog
D. Product Backlog, Sprint Backlog
The Sprint planning meeting is comprised of how many sections?
A. 4
B. 3
C. 2
D. 1
What is the maximum duration of each Sprint planning meeting section?
A. 1 hour
B. 30 minutes
C. 4 hours
D. 2 hours
E. 15 minutes
Which of the following activities do not occur at the end of the Sprint? (Choose two) A. Software development
B. Release deployment
C. Sprint review meeting
D. Quality assurance testing
What does the Scrum Development Team attempt to develop at every Sprint?
A. A product that is ready for customer delivery
B. A completed Sprint Backlog
C. A product that is ready for QA and/or QC testing
D. A product increment that is potentially-ready for customer delivery
Which of the following is not a Product Owner responsibility?
A. Maintaining the Product Backlog with current information
B. Working with stakeholders to determine and detail product features
C. Assigning tasks to team members
D. Prioritizing the Product Backlog
Who determines whether the development team has been assigned enough work in a Sprint?
A. The Development Team
B. The Product Owner
C. The Product Owner and the Scrum Master
D. The Scrum Master
________________ constitute the Sprint Backlog and are often estimated in hours?
A. User Stories
B. Use Cases
C. Features
D. Tasks
Under what circumstances should separate Product Backlogs be maintained?
A. There are several Product Owners for one product. Each Product Owner should have their own Product Backlog
B. There are multiple teams working on independent products. Each unique combination of team and product should have an independent Product Backlog
C. There are multiple product features being developed by the same team.
D. There are multiple teams working on the components of the same product. Each team should an independent Product Backlog
Which of the following is not a Scrum cycle activity?
A. Sprint retrospective
B. Daily scrum
C. Weekly inspection
D. Sprint planning
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CSM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.