Which of the following qualitative techniques involves a disciplined analysis of the event sequences that could transform a potential hazard into an accident?
A. Failure mode and effects criticality analysis
B. HAZOP technique
C. Failure mode and effects analysis
D. Preliminary Risk Analysis
Which of the following establishes organizational checks and balances with a proper segregation of front, back, and middle office functions for effective risk management?
A. Risk response plan
B. Risk analysis
C. Risk management plan
D. Risk governance
Which of the following roles works with the project team to understand the deliverables and then teaches the users of the deliverables how to utilize the project's product?
A. End user
B. Database analyst
C. Stakeholder
D. Trainer
Which of the following is a visual decomposition of the program scope and the resources needed in order to create the things defined within the program scope?
A. Resource breakdown structure (RBS)
B. product breakdown structure (PBS)
C. Budgeted Cost of Work Scheduled (BCWS)
D. Work Breakdown Structure (WBS)
When does the lessons learned document is updated?
A. At planning phase.
B. At execution phase.
C. At closing phase.
D. Throughout the project lifecycle.
Which of the following stages of a project defines the number of risks and opportunities, including intense planning and anticipation of risk events?
A. Planning
B. Executing
C. Initiation
D. Closing
Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?
A. Influence diagram
B. Project schedule network diagram
C. Arrow diagramming method
D. Time-scaled schedule network diagram
____ is a process to determine the completeness of the project work and to gain the customer's acceptance to move the project forward.
A. Phase gate review
B. Inspection of key results
C. Verify scope
D. Quality control
Which of the following phases is the first step towards creating a business continuity plan?
A. Business Continuity Plan Development
B. Scope and Plan Initiation
C. Business Impact Assessment
D. Plan Approval and Implementation
Which of the following charts is a quality control tool to show categories of defects?
A. Pareto chart
B. RACI chart
C. Gantt chart
D. RAM chart
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IIBA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CBAP exam preparations and IIBA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.