  • Question 221:

    Which of the following defines how the project will be estimated, budgeted, and how changes to cost will be managed?

    A. Cost management plan

    B. Cost variance reports

    C. Control chart

    D. Coercive power

  • Question 222:

    Which of the following techniques involves attempting to make and numerically determine the probability of various adverse events and measuring the likely extent of the losses?

    A. Risk analysis

    B. Qualitative risk analysis

    C. Risk assessment

    D. Quantitative risk analysis

  • Question 223:

    Which of the following captures all of the activities within a business, the inputs and outputs of each activity, and the required resources to complete each activity?

    A. Business scenario

    B. Business process model

    C. Business architecture

    D. Business case

  • Question 224:

    Which of the following is a graphical representation of roles and responsibilities of different project team members?

    A. RACI chart

    B. Pareto chart

    C. Resource histogram chart

    D. Organization chart

  • Question 225:

    Which one of the following diagrams visualize the result of the root cause analysis study?

    A. Activity diagrams

    B. State diagrams

    C. Tornado diagrams

    D. Cause-and effect diagrams

  • Question 226:

    The business process model is also known as _________.

    A. Organization model

    B. Activity model

    C. Relational model

    D. Data flow model

  • Question 227:

    Which of the following techniques is used to divide a project into controllable parts?

    A. Gantt Chart

    B. Pareto Chart

    C. WBS

    D. CPM

  • Question 228:

    Which of the following is a method of displaying the timelines of all the various subtasks that are involved in any project?

    A. Pie chart

    B. Scatter chart

    C. Activity network diagram

    D. Cost-benefit analysis

  • Question 229:

    Which of the following can be used in root cause analysis?

    A. Pareto chart

    B. Data-flow diagram

    C. Gantt chart

    D. Fishbone diagram

  • Question 230:

    Which of the following diagrams is known as Ishikawa diagram?

    A. Activity

    B. Data-flow

    C. Cost-Benefit

    D. Cause-and Effect

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IIBA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CBAP exam preparations and IIBA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.