  • Question 61:

    A soft reservation is a request that is defined by what?

    A. The priority of the work order

    B. A request for items for any job

    C. Items not subject to a timeframe

    D. The need for an item at a specific time

  • Question 62:

    What should be considered when voiding a receipt record in IBM Maximo Asset Management V7.5?

    A. Service receipts cannot be voided.

    B. A receipt can be voided for a partial quantity.

    C. Receipts for returned items cannot be voided.

    D. Only receipts for non-rotating items can be voided.

  • Question 63:

    How are items deleted from an active job plan?

    A. Delete the item and then save the record

    B. Make a job plan revision and then delete the item

    C. Change the job plan to WAPPR and then delete the item

    D. Change the job plan to PENDING and then delete the item

  • Question 64:

    When would an approved purchase order (PO) need to be revised?

    A. change of status

    B. change to an internal PO

    C. changes to quantity of items ordered

    D. cancellation of a PO after goods are received

  • Question 65:

    What if the projected forecast date for a preventive maintenance (PM) record occurs in an inactive season?

    A. The active season dates should be modified.

    B. The inactive season dates should be modified.

    C. The PM record is forecasted on the latest date in the next active season.

    D. The PM record is forecasted on the earliest date in the next active season.

  • Question 66:

    What are the three components that are used to construct a failure hierarchy within a failure class?

    A. Fixes

    B. Causes

    C. Incidents

    D. Problems

    E. Remedies

    F. Corrections

  • Question 67:

    What is the purpose of a Service Level Agreement?

    A. to determine a vendor's lead time

    B. to put a service request into workflow

    C. to escalate a high priority service request

    D. to document the commitment between service providers and customers

  • Question 68:

    A meter has been defined to observe the oil color on an asset to monitor its condition. Which meter type was used to accomplish this?

    A. Group meter

    B. Gauge meter

    C. Continuous meter

    D. Characteristic meter

  • Question 69:

    The actual start date on a service request is populated by the system when the record is changed to which status?

    A. NEW

    B. DRAFT

    C. INPROG

    D. QUEUED

  • Question 70:

    Which statement is true regarding ticket templates, job plans, and activities?

    A. Only job plans with a status of Active can be applied to ticket templates.

    B. Activities specified on a service request using a job plan cannot be deleted.

    C. A job plan can be applied by a ticket template or directly to the service request.

    D. Activities specified on a job plan are viewable on the Plans tab of the Service Request application.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IBM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C2010-595 exam preparations and IBM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.