According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time?
Reveal answer details Close answer details
Correct answerC
GAQM · CSM-001
Preview real exam questions, verified answers and available explanations before choosing a study plan.
|
Single choice
According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which topics should be discussed in the Sprint Review? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which role in Scrum is responsible to prioritize Product Backlog? Reveal answer details Close answer detailsCorrect answerC Explanation References:
Single choice
The Sprint Backlog is owned by? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following are activities found in the Scrum framework? Reveal answer details Close answer detailsCorrect answerB
Single choice
True or False: The sprint planning is a one-day time boxed meeting divided into two 4-hour sessions? Reveal answer details Close answer detailsCorrect answerA
Single choice
You are the new Scrum Master at a company currently doing RUP in three month iterations. Your current task in switching from RUP to Scrum is to define how long the Sprint cycle should be. Reveal answer details Close answer detailsCorrect answerC
Multiple choice
Which of these may a Development Team deliver at the end of a Sprint (choose 2)? Reveal answer details Close answer detailsCorrect answersA, D
Single choice
What is the major difference between Product Backlog and Sprint Backlog? Reveal answer details Close answer detailsCorrect answerC
Single choice
What happens when all committed items (requirements) are not completed at the end of the Sprint? Reveal answer details Close answer detailsCorrect answerC
Single choice
___________________is responsible for the Scrum process, facilitate the team and protect the team from outside noise. Reveal answer details Close answer detailsCorrect answerA
Single choice
Which objectives are covered as part of Sprint Planning? Reveal answer details Close answer detailsCorrect answerA
Single choice
More than one Scrum Team is working on a single project or release. How should the Product Backlog be arranged? Reveal answer details Close answer detailsCorrect answerB
Single choice
What is the maximum time that Scrum recommends the team spend in the daily scrum (daily standup)? Reveal answer details Close answer detailsCorrect answerA
Single choice
The term Agile Development was first introduced in: Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following meeting is not part of Scrum? Reveal answer details Close answer detailsCorrect answerC
Single choice
You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks? Reveal answer details Close answer detailsCorrect answerA
Multiple choice
Which of the following are valid Scrum Meetings? (Choose four.) Reveal answer details Close answer detailsCorrect answersA, B, E, F Explanation References:
Multiple choice
In an Agile environment, planning happens at which two levels? (Choose two.) Reveal answer details Close answer detailsCorrect answersA, C
Single choice
Which statement below best describes the primary objective of the Sprint Review? Reveal answer details Close answer detailsCorrect answerB |