Which of the following are inputs for the Plan Quality Management processes?
Reveal answer details Close answer details
Correct answerC
PMI ยท CAPM
Review the question wording, option layout, and available explanations before choosing a study plan.
|
Single choice
Which of the following are inputs for the Plan Quality Management processes? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following statements correctly characterizes pull communication? Reveal answer details Close answer detailsCorrect answerB
Single choice
What is an example of an emerging trend in procurement management? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following is an input to the Perform Qualitative Risk Analysis process? Reveal answer details Close answer detailsCorrect answerA
Single choice
Directing another person to get from one to another using a known set of expected behaviors are the ability to lead a team and inspire them to do their jobs well is related to? Reveal answer details Close answer detailsCorrect answerC
Single choice
The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy? Reveal answer details Close answer detailsCorrect answerA
Single choice
When establishing a contingency reserve, including time, money and resources, how is the risk being handled? Reveal answer details Close answer detailsCorrect answerD
Single choice
What organizational process asset (OPA) can impact a project? Reveal answer details Close answer detailsCorrect answerB
Drag & drop
DRAG DROP A project manager is reviewing the different tools and techniques used to perform a quantitative risk analysis. Match the tool and techniques with the appropriate result. ![]() Reveal answer details Close answer details![]()
Single choice
Which set of competencies should a project manager have? Reveal answer details Close answer detailsCorrect answerA
Single choice
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)? Reveal answer details Close answer detailsCorrect answerB Explanation SV=EV-PV
Single choice
Which of the following are documented directions to perform an activity that can reduce the probability of negative consequences associated with project risks? Reveal answer details Close answer detailsCorrect answerB
Single choice
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within: Reveal answer details Close answer detailsCorrect answerD
Single choice
When the business objectives of an organization change, project goals need to be: Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the following is a project constraint? Reveal answer details Close answer detailsCorrect answerD
Single choice
Taking out insurance in relation to risk management is called what? Reveal answer details Close answer detailsCorrect answerA
Single choice
A procurement management plan is a subsidiary of which other type of plan? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following is used as input to prepare a cost management plan? Reveal answer details Close answer detailsCorrect answerD
Single choice
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process? Reveal answer details Close answer detailsCorrect answerB
Single choice
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as: Reveal answer details Close answer detailsCorrect answerD
Single choice
The project scope statement and resource calendars are inputs to which Project Time Management process? Reveal answer details Close answer detailsCorrect answerC
Single choice
A project manager needs to determine the schedule variance (SV). The project manager's latest schedule indicates 14 units of work completed against a plan of 23 units. What is the SV? Reveal answer details Close answer detailsCorrect answerD Explanation EV = 14 SV = EV - PV
Single choice
The process of identifying specific actions to be performed to produce project deliverables is: Reveal answer details Close answer detailsCorrect answerA
Single choice
A reward can only be effective if it is: Reveal answer details Close answer detailsCorrect answerD
Single choice
Which output is the approved version of the time-phased project budget? Reveal answer details Close answer detailsCorrect answerD
Single choice
A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints. How many sprints are needed to complete the work? Reveal answer details Close answer detailsCorrect answerA
Single choice
What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders? Reveal answer details Close answer detailsCorrect answerA
Single choice
The basis of identification for current or potential problems to support later claims or new procurements is provided by: Reveal answer details Close answer detailsCorrect answerC
Single choice
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects? Reveal answer details Close answer detailsCorrect answerD
Single choice
A project manager is assigned to a strategic project. Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project. Which entities will the project manager attempt to influence? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy? Reveal answer details Close answer detailsCorrect answerC
Single choice
Assigned risk ratings are based upon: Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following technology platforms is most effective for sharing information when managing virtual project teams? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which degree of authority does a project manager have on a project in a strong matrix organizational structure? Reveal answer details Close answer detailsCorrect answerC
Single choice
A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using? Reveal answer details Close answer detailsCorrect answerD
Single choice
The Monitoring and Controlling Process Group includes processes that: Reveal answer details Close answer detailsCorrect answerC
Single choice
What is an emerging practice in stakeholder engagement? Reveal answer details Close answer detailsCorrect answerA
Single choice
In Project Cost Management, which input is exclusive to the Determine Budget process? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which document includes the project scope, major deliverables, assumptions, and constraints? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized? Reveal answer details Close answer detailsCorrect answerC
Single choice
Skills necessary for project management such as motivating to provide encouragement; listening actively; Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives? Reveal answer details Close answer detailsCorrect answerD
Single choice
Enterprise environmental factors are an input to which process? Reveal answer details Close answer detailsCorrect answerC
Single choice
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process? Reveal answer details Close answer detailsCorrect answerB
Single choice
The process of prioritizing risks for further analysis or action is known as: Reveal answer details Close answer detailsCorrect answerC
Single choice
A project's business analyst has to understand the newly acquired technology and the impact it will have on the organization. Which tool should be used to understand the new technology? Reveal answer details Close answer detailsCorrect answerA
Single choice
What cost control technique is used to compare actual project performance to planned or expected performance? Reveal answer details Close answer detailsCorrect answerD
Single choice
The following chart contains information about the tasks in a project. Based on the chart, what is the schedule performance index (5PI) for Task 4? Reveal answer details Close answer detailsCorrect answerC
Single choice
A project reports an earned value (EV) of US$45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which process is engaged when a project team member makes a change to project budget with the project manager's approval? Reveal answer details Close answer detailsCorrect answerD
Single choice
A process is defined as: Reveal answer details Close answer detailsCorrect answerA
Single choice
The project manager has the following information about the estimated duration for an activity: Most likely [tM] `" 15 days Pessimistic [tP] `" 20 days Optimistic [tO] `" 10 days What is the estimated duration of this activity, according to the triangular distribution technique? Reveal answer details Close answer detailsCorrect answerB
Single choice
Monte Carlo is which type of risk analysis technique? Reveal answer details Close answer detailsCorrect answerB
Single choice
During which process of Project Cost Management does a project manager produce the cost baseline? Reveal answer details Close answer detailsCorrect answerC
Single choice
The purpose of the Project Communications Management Knowledge Area is to: Reveal answer details Close answer detailsCorrect answerD
Single choice
Which document can help a project manager to leverage historical project information? Reveal answer details Close answer detailsCorrect answerA
Single choice
What is the total float of the critical path? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which process determines the correctness of deliverables? Reveal answer details Close answer detailsCorrect answerA
Single choice
Information collected on the status of project activities being performed to accomplish the project work is known as what? Reveal answer details Close answer detailsCorrect answerB
Single choice
Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which contract type is least desirable to a vendor? Reveal answer details Close answer detailsCorrect answerB
Drag & drop
DRAG DROP Match the process with its corresponding process group. ![]() Reveal answer details Close answer details![]() Explanation References:
Single choice
An input required to develop a preliminary project scope statement is: Reveal answer details Close answer detailsCorrect answerB
Single choice
A project team identifies defects that will require a modification to a tool's functionality. What process should the project manager follow to obtain stakeholder buy-in? Reveal answer details Close answer detailsCorrect answerB
Single choice
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which process occurs within the Monitoring and Controlling Process Group? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which process uses expert judgment to manage project resources? Reveal answer details Close answer detailsCorrect answerD
Single choice
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as: Reveal answer details Close answer detailsCorrect answerC
Single choice
An organization is faced with increasing demand from the board of directors. They say budgets are exible as long as the work gets completed. What project management approach should the organization use? Reveal answer details Close answer detailsCorrect answerC
Single choice
A disadvantage associated with virtual teams is that they: Reveal answer details Close answer detailsCorrect answerD
Single choice
An adaptive project manager is migrating the company's new website. The project manager must work with the team to invest full capacity on this project because it is the company's top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects. How should the project manager assign the team members to this project? Reveal answer details Close answer detailsCorrect answerA
Single choice
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to? Reveal answer details Close answer detailsCorrect answerD
Single choice
Why is working in iterations usually more time consuming than using a predictive life cycle? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which of the following documents should the project manager update as a result of implementing the Plan Risk Responses process? Reveal answer details Close answer detailsCorrect answerD
Single choice
An input to the Create WBS process is a: Reveal answer details Close answer detailsCorrect answerC
Single choice
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which item is an example of personnel assessment? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which technique is commonly used for the Perform Quantitative Risk Analysis process? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following is the primary output of the Identify Risks process? Reveal answer details Close answer detailsCorrect answerB
Single choice
What tool or technique will establish expected behaviors for project team members? Reveal answer details Close answer detailsCorrect answerA
Single choice
Calculate the schedule performance index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15. Reveal answer details Close answer detailsCorrect answerD
Single choice
An input of the Control Schedule process is the: Reveal answer details Close answer detailsCorrect answerD
Single choice
Analytical techniques are a tool and technique of which process in Project Procurement Management? Reveal answer details Close answer detailsCorrect answerC
Single choice
Agile release planning provides a high-level summary timeline of the release schedule based on: Reveal answer details Close answer detailsCorrect answerC
Single choice
An output of the Plan Quality Management process is: Reveal answer details Close answer detailsCorrect answerA
Single choice
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following Process Groups covers all Project Management Knowledge Areas? Reveal answer details Close answer detailsCorrect answerC
Single choice
What happens to a stakeholder's project influence over time? Reveal answer details Close answer detailsCorrect answerB
Single choice
In which type of organizational structure are staff members grouped by specialty? Reveal answer details Close answer detailsCorrect answerA
Single choice
In a project, total float measures the: Reveal answer details Close answer detailsCorrect answerB
Single choice
Which of the following items is a technique for data gathering? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which organizational process assets update is performed during the Close Procurements process? Reveal answer details Close answer detailsCorrect answerB
Single choice
Organizations perceive risks as: Reveal answer details Close answer detailsCorrect answerB
Single choice
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which scenario is most desirable during the execution phase of a project? Reveal answer details Close answer detailsCorrect answerA
Single choice
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as: Reveal answer details Close answer detailsCorrect answerA |