You are implementing SAP S/4HANA and you want to run analytical reports off a single data model.
Which statement best describes reporting in SAP S/4HANA?
Reveal answer details Close answer details
Correct answerC
SAP ยท C_TS4CO_2021
Review the question wording, option layout, and available explanations before choosing a study plan.
|
Single choice
You are implementing SAP S/4HANA and you want to run analytical reports off a single data model. Which statement best describes reporting in SAP S/4HANA? Reveal answer details Close answer detailsCorrect answerC
Single choice
You have implemented Product Cost by Sales Oder in conjunction with cost-based POC results analysis in your organization. For a particular sales order item, you have the following: Plan revenue = 3000; Plan costs = 2000 Actual revenue = 1200; Actual cost=1000 What data does the system calculate during results analysis? Reveal answer details Close answer detailsCorrect answerC
Single choice
You would like to allocate primary and secondary costs from a cost center to another cost center. Which allocation method will you use? Reveal answer details Close answer detailsCorrect answerA
Multiple choice
Which of the following objects can be selected in templates for activity-based costing? Note: There are 2 correct answers to this question. Reveal answer details Close answer detailsCorrect answersB, C
Single choice
In a standard system delivery, how many free characteristics can be added to an operating concern? Reveal answer details Close answer detailsCorrect answerA
Single choice
What can you do with statistical internal orders? Reveal answer details Close answer detailsCorrect answerC
Multiple choice
Which processes split costs into their primary cost components? Note: There are 2 correct answers to this question. Reveal answer details Close answer detailsCorrect answersB, D
Single choice
What do you need to setup in order to bring the values incoming sales orders into account-based Profitability Analysis? Reveal answer details Close answer detailsCorrect answerD
Single choice
You want to create a new standard cost estimate based on the quantity structure of the existing standard cost estimate. Which object do you use? Reveal answer details Close answer detailsCorrect answerC
Multiple choice
How does the system derive the requirement type from the material master data? Note: There are 2 correct answers to this question. Reveal answer details Close answer detailsCorrect answersB, D
Multiple choice
How can you define the overhead rate in a costing sheet? Note: There are 2 correct answers to this question. Reveal answer details Close answer detailsCorrect answersB, D
Multiple choice
You are creating new activity type and want to maintain plan prices for a cost center. Reveal answer details Close answer detailsCorrect answersB, D, E |