Change request status updates are an output of which process?
Reveal answer details Close answer details
Correct answerA
GAQM · APM-001
Preview real exam questions, verified answers and available explanations before choosing a study plan.
|
Single choice
Change request status updates are an output of which process? Reveal answer details Close answer detailsCorrect answerA
Single choice
At which point of the project is the uncertainty the highest and the risk of failing the greatest? Reveal answer details Close answer detailsCorrect answerB
Single choice
Testing falls into which of the following categories of cost of quality? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following Project Communication Management processes uses performance reports as an input? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following response strategies are appropriate for negative risks or threats? Reveal answer details Close answer detailsCorrect answerD
Single choice
After Define Activities and Sequence Activities, the next process is: Reveal answer details Close answer detailsCorrect answerA
Single choice
Which is an output from Distribute Information? Reveal answer details Close answer detailsCorrect answerC
Single choice
A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. Reveal answer details Close answer detailsCorrect answerA
Single choice
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process? Reveal answer details Close answer detailsCorrect answerB
Single choice
A tool or technique used in the Control Procurements process is: Reveal answer details Close answer detailsCorrect answerB
Single choice
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as: Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders? Reveal answer details Close answer detailsCorrect answerC
Single choice
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information? Reveal answer details Close answer detailsCorrect answerB
Single choice
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating? Reveal answer details Close answer detailsCorrect answerA
Single choice
During which process would stakeholders provide formal acceptance of the completed project scope? Reveal answer details Close answer detailsCorrect answerB
Single choice
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the following is a narrative description of products, services, or results to be delivered by a project? Reveal answer details Close answer detailsCorrect answerA
Single choice
Documented identification of a flaw in a project component together with a recommendation is termed a: Reveal answer details Close answer detailsCorrect answerD
Single choice
When is a project finished? Reveal answer details Close answer detailsCorrect answerC
Single choice
Work performance information and cost forecasts are outputs of which Project Cost Management process? Reveal answer details Close answer detailsCorrect answerD
Single choice
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as: Reveal answer details Close answer detailsCorrect answerA
Single choice
Co-location is a tool and technique of: Reveal answer details Close answer detailsCorrect answerC
Single choice
When would resource leveling be applied to a schedule model? Reveal answer details Close answer detailsCorrect answerC
Single choice
A project manager should document the escalation path for unresolved project risks in the: Reveal answer details Close answer detailsCorrect answerD
Single choice
The process of identifying the stakeholders' information needs is completed during: Reveal answer details Close answer detailsCorrect answerA
Single choice
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the following techniques is used during Control Scope? Reveal answer details Close answer detailsCorrect answerB
Single choice
The following is a network diagram for a project. ![]() The total float for the project is how many days? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which activity may occur at project or phase closure? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which type of chart is a graphic representation of a process showing the relationships among process steps? Reveal answer details Close answer detailsCorrect answerC
Single choice
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document? Reveal answer details Close answer detailsCorrect answerC
Single choice
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process? Reveal answer details Close answer detailsCorrect answerC
Single choice
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an: Reveal answer details Close answer detailsCorrect answerA
Single choice
Which process determines the risks that may affect the project and documents their characteristics? Reveal answer details Close answer detailsCorrect answerD
Single choice
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is: Reveal answer details Close answer detailsCorrect answerA
Single choice
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which process occurs within the Monitoring and Controlling Process Group? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which tool or technique is used in Close Procurements? Reveal answer details Close answer detailsCorrect answerD
Single choice
A method to manage stakeholder expectations in the scope statement is to clearly: Reveal answer details Close answer detailsCorrect answerC
Single choice
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the: Reveal answer details Close answer detailsCorrect answerB
Single choice
The basis of identification for current or potential problems to support later claims or new procurements is provided by: Reveal answer details Close answer detailsCorrect answerC
Single choice
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements? Reveal answer details Close answer detailsCorrect answerB
Single choice
The following is a network diagram for a project. Reveal answer details Close answer detailsCorrect answerA
Single choice
The purpose of the Project Communications Management Knowledge Area is to: Reveal answer details Close answer detailsCorrect answerD
Single choice
What is the most accurate rough order of magnitude (ROM)? Reveal answer details Close answer detailsCorrect answerA
Single choice
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a: Reveal answer details Close answer detailsCorrect answerB
Single choice
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering? Reveal answer details Close answer detailsCorrect answerA
Single choice
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation? Reveal answer details Close answer detailsCorrect answerA
Single choice
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning: Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract? Reveal answer details Close answer detailsCorrect answerB
Single choice
Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of: Reveal answer details Close answer detailsCorrect answerA
Single choice
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used? Reveal answer details Close answer detailsCorrect answerC
Single choice
Activity cost estimates and the project schedule are inputs to which Project Cost Management process? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which is one of the major outputs of Sequence Activities? Reveal answer details Close answer detailsCorrect answerC
Single choice
Through whom do project managers accomplish work? Reveal answer details Close answer detailsCorrect answerD
Single choice
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called: Reveal answer details Close answer detailsCorrect answerD
Single choice
External organizations that have a special relationship with the enterprise and provide specialized expertise are called: Reveal answer details Close answer detailsCorrect answerB
Single choice
Which tool or technique is used in the Perform Integrated Change Control process? Reveal answer details Close answer detailsCorrect answerD
Single choice
Quality metrics are an output of which process? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship? Reveal answer details Close answer detailsCorrect answerB
Single choice
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of: Reveal answer details Close answer detailsCorrect answerC
Single choice
Which is an output of the Collect Requirements process? Reveal answer details Close answer detailsCorrect answerA
Single choice
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as: Reveal answer details Close answer detailsCorrect answerC
Single choice
Which of the following factors is lowest at the start of the project? Reveal answer details Close answer detailsCorrect answerA
Single choice
An output of Control Schedule is: Reveal answer details Close answer detailsCorrect answerD
Single choice
An input of the Plan Procurement Management process is: Reveal answer details Close answer detailsCorrect answerB
Single choice
"Tailoring" is defined as the: Reveal answer details Close answer detailsCorrect answerA
Single choice
During which process does the project team receive bids and proposals? Reveal answer details Close answer detailsCorrect answerA
Single choice
An input to the Create WBS process is a: Reveal answer details Close answer detailsCorrect answerC
Single choice
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project? Reveal answer details Close answer detailsCorrect answerC
Single choice
The probability and impact matrix is primarily used to: Reveal answer details Close answer detailsCorrect answerC
Single choice
The creation of an internet site to engage stakeholders on a project is an example of which type of communication? Reveal answer details Close answer detailsCorrect answerB
Single choice
Portfolio Management is management of: Reveal answer details Close answer detailsCorrect answerD
Single choice
An output of the Develop Project Team process is: Reveal answer details Close answer detailsCorrect answerB
Single choice
The Human Resource Management processes are: Reveal answer details Close answer detailsCorrect answerA
Single choice
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity? Reveal answer details Close answer detailsCorrect answerC
Single choice
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)? Reveal answer details Close answer detailsCorrect answerC
Single choice
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which item is a formal proposal to modify any document, deliverable, or baseline? Reveal answer details Close answer detailsCorrect answerA
Single choice
For a stakeholder with low interest and high power, the project manager should: Reveal answer details Close answer detailsCorrect answerC
Single choice
An example of a group decision-making technique is: Reveal answer details Close answer detailsCorrect answerB
Single choice
Analogous cost estimating relies on which of the following techniques? Reveal answer details Close answer detailsCorrect answerA
Single choice
The following is a network diagram for a project. ![]() The critical path for the project is how many days in duration? Reveal answer details Close answer detailsCorrect answerD
Single choice
Which type of managers do composite organizations involve? Reveal answer details Close answer detailsCorrect answerA
Single choice
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success? Reveal answer details Close answer detailsCorrect answerD
Single choice
The project management processes presented in the PMBOK Guide?should: Reveal answer details Close answer detailsCorrect answerC
Single choice
Which process involves identifying and documenting the logical relationships between project activities? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which Process Group contains those processes performed to define a new project? Reveal answer details Close answer detailsCorrect answerA
Single choice
Which process should be conducted from the project inception through completion? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which is one of the determining factors used to calculate CPI? Reveal answer details Close answer detailsCorrect answerA
Single choice
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group? Reveal answer details Close answer detailsCorrect answerB
Single choice
Managing procurement relationships and monitoring contract performance are part of which process? Reveal answer details Close answer detailsCorrect answerC
Single choice
Which type of organizational structure is displayed in the diagram provided? ![]() Reveal answer details Close answer detailsCorrect answerB
Single choice
Which tool or technique is an examination of industry and specific vendor capabilities? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which type of dependency is contractually required or inherent in the nature of the work? Reveal answer details Close answer detailsCorrect answerD
Single choice
In which process might a project manager use risk reassessment as a tool and technique? Reveal answer details Close answer detailsCorrect answerB
Single choice
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management? Reveal answer details Close answer detailsCorrect answerB |