What are two differences between an issue and a task? (Choose two.)
Reveal answer details Close answer details
Correct answersA, C
Adobe · AD0-E908
Preview real exam questions, verified answers and available explanations before choosing a study plan.
|
Multiple choice
What are two differences between an issue and a task? (Choose two.) Reveal answer details Close answer detailsCorrect answersA, C
Multiple choice
A client has employees based in both India (1-10 1ST) and the United States (8-5 EST) who are working together on a project. Which two options help the Project calculate timelines and user availability correctly9 (Choose two.) Reveal answer details Close answer detailsCorrect answersC, D
Single choice
On which types of objects can time be recorded in Workfront? Reveal answer details Close answer detailsCorrect answerC
Single choice
What is one of the primary benefits to setting up an automated proofing workflow instead of a basic workflow? Reveal answer details Close answer detailsCorrect answerB
Multiple choice
A system administrator is using layout templates to optimize the user experience in Workfront. What two best practices should be considered to help drive adoption? (Choose two.) Reveal answer details Close answer detailsCorrect answersC, D
Single choice
What license types in Workfront allow a user to create, edit, and delete reports? Reveal answer details Close answer detailsCorrect answerC
Multiple choice
Aside from predecessors, resource manager assignments, and system administrator settings, what are three prerequisites for using the Resource Planner and Workload Balancer? (Choose three.) Reveal answer details Close answer detailsCorrect answersA, B, C
Single choice
A project team has configured a Kanban board with columns for backlog, in progress, on hold, and completed statuses. The project manager wishes to automatically archive cards that have been closed for longer than two weeks. What should the project manager change in order to make this happen? Reveal answer details Close answer detailsCorrect answerA
Single choice
An Adobe Workfront system administrator is asked to fix an external web page on a dashboard. The URL for the desired content no longer points to the correct page. How can the system administrator update the link for the external page? Reveal answer details Close answer detailsCorrect answerA
Single choice
Where in the standard report builder can a person use a Wildcard? Reveal answer details Close answer detailsCorrect answerA
Single choice
A project manager is using information in the Portfolio Optimizer to analyze which projects to prioritize. Where is this information coming from? Reveal answer details Close answer detailsCorrect answerA |