Which three variables are used with Earned Value?
Reveal answer details Close answer details
Correct answersA, B, C
EV -earned value, estimated value of work done.
PV -planned value, estimated value of planned work AC -actual cost, what you paid
Oracle · 1Z0-466
Preview real exam questions, verified answers and available explanations before choosing a study plan.
|
Multiple choice
Which three variables are used with Earned Value? Reveal answer details Close answer detailsCorrect answersA, B, C Explanation EV -earned value, estimated value of work done.
Single choice
What work product, created by the Project Manager and the client, details the approach to the project at a high level? Reveal answer details Close answer detailsCorrect answerE Explanation Activities allow the project manager to streamline creation and management of the Work BreakdownStructure (WBS) for an engagement. Note:
Multiple choice
Select the three goals that have been set for Oracle Unified Method (OUM). Reveal answer details Close answer detailsCorrect answersB, C, E Explanation Note:
Multiple choice
Select the two plans that are always active in the project at any given time. Reveal answer details Close answer detailsCorrect answersC, D Explanation There are two plans active in the project at any given time ?the implementation plan and the iteration plan.
Single choice
Which term means monitoring specific results to determine whether they comply with the relevant standards? Reveal answer details Close answer detailsCorrect answerD
Multiple choice
Select three objectives of the OUM Envision phase. Reveal answer details Close answer detailsCorrect answersB, D, F Explanation Note: Governance
Multiple choice
Which three items must be updated when scope changes are approved? Reveal answer details Close answer detailsCorrect answersA, B, E Explanation Note:
Multiple choice
Select three types of Envision engagements. Reveal answer details Close answer detailsCorrect answersA, C, D Explanation The Envision focus area provides a framework for development and maintenance of enterprise level IT strategy, architecture, and governance. The Envision guidance helps project team's transition from enterprise-level planning and strategy activities to the identification and initiation of specific projects.
Single choice
According to the recommended training for this exam, an engagement becomes a project when . Reveal answer details Close answer detailsCorrect answerB
Single choice
Which statement is true about the Project Management Plan and the Project Workplan in OUM? Reveal answer details Close answer detailsCorrect answerB Explanation *OUM Manage provides the framework for consistently managing a project regardless of the project approach. The project manager must be familiar with the project approach being used, and must make the necessary adjustments in the Project Management Plan (as well as in the Project Workplan) to incorporate the concepts and activities that support the given approach.The same concepts apply to projects using offshore resources or third parties. *OUM Manage and Other Project Approaches OUM Manage can be used with any project approach. OUM Manage does not required any specific project approach. The project manager should adjust the Project Management Plan and Project Workplan in order to execute the project following the designated project approach.
Multiple choice
Earned value is a technique to report project status using which three variables? Reveal answer details Close answer detailsCorrect answersA, B, C Explanation EV -earned value, estimated value of work done.
Multiple choice
Which two statements are true about the Project Management Plan during the Project Execution and Control Phase? Reveal answer details Close answer detailsCorrect answersB, D
Single choice
According to the recommended training for this exam, what is the "triple constraint"? Reveal answer details Close answer detailsCorrect answerA Explanation *Scope, Time & Cost together are termed as the Triple Constraints of a Project. *Risk avoidance involves changing the project plan to eliminate therisk or to protect the project objectives (time, cost, scope, quality) from itsimpact. The team might achieve this by changing scope, adding time, oradding resources (thus relaxing the so-called "triple constraint") Note: ![]()
Multiple choice
Which two items are completed during the Work Management close? Reveal answer details Close answer detailsCorrect answersA, C Explanation Note:Work Management - The objective of the Work Management process is to develop the work plan and to define and document the processes and policies to be used to execute, maintain, control and close-out the Project Workplan.
Multiple choice
Select two objectives of the OUM Implement Elaboration phase. Reveal answer details Close answer detailsCorrect answersB, C Explanation The goal of the Elaboration phase is to develop the detailed requirements, partition the solution, create any necessary prototypes, and baseline the architecture of the system. This effort results in a stable basis for the design and implementation effort in the Construction phase. The architecture evolves from the most significant requirements(B), those that have the greatest impact on the architecture of the system, and an assessment of risk. The stability of the architecture is evaluated through one or more architectural prototypes. During the Elaboration phase, the project team's understanding of the client's business requirements is verified to reduce development risk. Note: |